    How Equinor achieved on-time handover for FPSO Bacalhau

    A CONVERSATION WITH
    Erik Nordström

    Erik Nordström

    Head of Commissioning Operations

    EQUINOR case study
    EQUINOR

    About

    Equinor is a broad energy company with operations in over 30 countries, developing oil, gas, wind and solar energy.

    Industry

    Oil & Gas

    Company size

    21,000+

    Headquarters

    Stavanger, Norway

    Founded

    1972

    Funding raised

    Public Company

    Key features

    System completions
    Punch tracking
    Handover workflows

    The Challenge

    What they faced

    Equinor was facing significant challenges in managing the commissioning and handover process for FPSO Bacalhau. With thousands of systems to track and multiple contractors involved, they needed a unified platform to ensure visibility and accountability across all stakeholders.

    The Solution

    How Deskely helped

    Implement Deskely as the central platform for all commissioning activities, enabling real-time tracking of ITRs, punch items, and system completions. The platform provided automated workflows and notifications to keep all teams aligned.

    The Results

    Measurable impact

    100% on-time system handovers achieved across all critical systems

    45% reduction in punch item resolution time compared to previous projects

    Over 2,500 hours saved in documentation and reporting workflows

    Unified visibility across 12 contractor organizations

    Full Story

    Equinor's story

    Equinor embarked on the FPSO Bacalhau project with ambitious timelines and complex coordination requirements. As one of the largest deepwater developments in the Santos Basin, the project involved multiple contractors, thousands of equipment items, and stringent regulatory requirements.

    The commissioning team recognized early that traditional spreadsheet-based tracking would not scale to meet the project's demands. They needed a digital solution that could provide real-time visibility while maintaining the rigorous documentation standards required for offshore operations.

    After evaluating several options, Equinor selected Deskely as their commissioning management platform. The implementation began six months before the critical commissioning phase, allowing teams to familiarize themselves with the system and establish standardized workflows.

    The results exceeded expectations. Not only did the project achieve on-time handover, but the efficiency gains freed up engineering resources to focus on optimization rather than administrative tasks. The success of FPSO Bacalhau has become a model for Equinor's future projects.