Base build now, suites and cages on a schedule of their own

    Colocation commissioning software for facilities that hand over capacity to tenants in stages, not all at once.

    A colocation facility commissions its base build — power, cooling and BMS — once, then repeats a smaller commissioning cycle for every suite, cage or pod as tenants take capacity. Deskely keeps the base build register and the per-tenant SLA acceptance records connected, so a new suite can be proven against the shared infrastructure without re-litigating what the base build already demonstrated.

    Scope
    Base build plus per-suite fit-out
    Parties
    Operator, MEP, tenant reps
    Cadence
    Continuous suite hand-offs
    Gate
    SLA acceptance per suite
    SUITE 4 — MULTI-TENANT FLOORTENANT ACCEPTANCE PACK · REV CCAGE B-03metered feedaccess ctrlCAGE B-05metered feedaccess ctrlCAGE B-07metered feedaccess ctrlSB-CG04-PWR36 cages, independently meteredTAG REGISTERPDU-4.02PDU board, suite 4Records signedBUSWAY-4BOverhead busway, row BIn testCRAH-19Suite 4 air handlerPreservationRACK-4-118Tenant cabinet 118Punch open64 boardsunder one system hierarchy

    The problem

    The base build is proven once, but every new tenant wants their own proof.

    A colocation operator commissions the shared UPS, switchgear, chiller plant and BMS during base build, then has to demonstrate to each incoming tenant that the capacity, redundancy and monitoring they're paying for actually holds for their suite specifically.

    Without a shared register, every tenant acceptance becomes a fresh spreadsheet exercise, re-proving facts about shared infrastructure that were already established months earlier.

    Deskely keeps the base build record set as the foundation every suite's acceptance references, so tenant SLA testing only has to prove what's actually new: the suite's PDUs, cooling units and monitoring points.

    PROVEN ONCE, RE-PROVEN PER TENANTSuite 4B — new tenant acceptanceBASE BUILD — PROVEN 8 MONTHS AGOUtility switchgearChiller plantSite UPSCampus BMS/EPMSTENANT WANTS IT RE-PROVEN, SUITE 4BRe-test shared UPS capacityAlready provenRe-test chiller redundancyAlready provenRe-run BMS points-to-graphicsAlready provenshared facts re-tested per new tenant1base build record set, referenced not repeatedSuite acceptance references the base build's own signed evidence instead of re-testing it.

    Setting up the register

    Base build infrastructure and tenant white space are separate subsystems with a shared dependency.

    Utility switchgear, generators, UPS, chiller plant and the site-wide BMS/EPMS sit in the base build subsystem; each suite, cage or pod is its own subsystem referencing the base build systems it draws from.

    Single-line diagrams and mechanical schedules for both base build and each fit-out are parsed into the register, so a suite's PDU is tagged against the upstream busway and UPS it depends on.

    That link is what lets a new suite's acceptance certificate cite the base build's Level 4/5 test results instead of re-testing shared plant every time a tenant signs a lease.

    1 · SOURCE DOCUMENTSSuite fit-out drawings r…8 suitesPDU and busway schedule64 boardsRack and cabinet list1 240 racksTenant SLA matrix14 tenantsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERPDU-4.02PDU board, suite 4SUITE 4BUSWAY-4BOverhead busway, row BSUITE 4CRAH-19Suite 4 air handlerMECHANICALRACK-4-118Tenant cabinet 118WHITE SPACETWO DOCUMENTS DISAGREESuite fit-out dra…Suite 4 air handlerPDU and busway sc…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Per-suite SLA acceptance

    Load bank testing, power quality and cooling capacity are proven against the SLA the tenant actually signed.

    Suite-level acceptance runs load bank tests against contracted kW, verifies redundant power paths to the rack (A/B feed, dual PDU), and confirms CRAC/CRAH capacity and containment against the design heat load for that suite.

    Punch raised during suite acceptance is categorised against whether it blocks the tenant's go-live date, distinct from base build punch that may still be open elsewhere on the floor.

    Because every suite follows the same templated record set, the tenth suite handed over takes the same rigour as the first without taking the same time.

    BASE BUILD ONCE, SUITE ACCEPTANCE ON REPEATSuite cadenceBase build — proven onceUtility, chiller plant, site UPS, campus BMS/EPMSSigned, referenced by every suite belowSuite 2A100%Suite 2B100%Suite 4B (in progress)62%Suite 5A (queued)0%2 of 4suites at SLA acceptance0base build re-tests per suiteEvery suite's SLA acceptance only proves what's genuinely new to that suite.

    Hand-off to the tenant

    Each tenant receives a dossier scoped to their suite, not the whole facility.

    Tenants rarely need or want visibility into the operator's whole facility register — they need evidence that their own suite meets the contracted SLA: redundancy, capacity, monitoring points and response commitments.

    Deskely exports a per-suite dossier referencing the shared base build evidence it depends on, which satisfies audit and due-diligence requests without exposing the rest of the facility's records.

    The same structure supports re-certification when a tenant expands or the operator upgrades shared plant, because the dependency between suite and base build is already modelled.

    AUDIT QUERYPDU-4.02Suite 4 · PDU boardFull history retrieved in one queryINSTInstallation recordElectrical contractor18 MarL2Pre-functional checklistCxA28 MarL4Functional performance testCxA12 AprFAILN+1 failover testVendor engineer20 AprCERTIFICATETATenant acceptancependingFacility operations managerPrerequisites demonstratedThe tenant acceptance certificate exports the day the suite is handed over, not the week after.

    The SLA is a legal document, not a target

    Every minute of downtime against the SLA has a financial consequence, and the operator has to be able to prove the number before the tenant disputes it.

    A colocation contract's uptime guarantee — 99.99%, 99.999%, whatever the tier — is backed by service credits the operator pays out the moment a tenant's suite drops below the contracted availability, and the first thing a dispute turns on is whether the operator can produce dated, signed evidence of what the infrastructure was actually delivering at the time.

    SOC 2 Type II and ISO 27001 auditors ask the same underlying question from a different angle: not just whether a control exists, but whether there is a continuous, tamper-evident record proving it operated as designed across the audit period, for every suite, not a sample.

    Deskely's per-suite acceptance record becomes that evidence base — load bank results, redundant feed verification and monitoring point history stay attached to the suite indefinitely, so an SLA credit dispute or an annual SOC 2 walkthrough is answered from the register rather than reconstructed from whichever engineer remembers the incident.

    ACCEPTANCE AGAINST THE SIGNED SLASuite 4B — 250 kW contractedOnly the suite's own contracted capacity and redundancy are testedSLA — SUITE 4B250 kW · A/B redundant feed · N+1 coolingContract clause 6.2SUITE ACCEPTANCE TESTSLoad bank test at contracted kWA/B feed redundancy to the rackCRAC/CRAH capacity vs suite heat loadContainment integrity, suite 4BOpen250 kWload bank result measured at the suite3 of 4SLA clauses proven this cycleBase build evidence is referenced, not re-tested — only what's new to this suite is proven.Acceptance certificate cites the contracted SLA clause each test satisfies.

    Evidence

    The suite acceptance dossier

    Colocation runs on continuous suite-by-suite hand-offs, each closed out against its own SLA, so the evidence pack for suite twelve has to stand alone from the base build pack rather than referencing it.

    RECORDS PRODUCED6 typesSuite-level power path…Before the suite is offered for tenant…Redundancy re-verification recordAfter each suite energisationLoad bank commissioning report for…Immediately prior to tenant SLA…Environmental monitoring and alarm…Ahead of suite handoverLevel 5 integrated systems test…Referenced at each new suite acceptanceSLA acceptance and witness packFinal gate before the suite goes liveDOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Suite-level power path verification report

    The tenant's A and B feeds trace correctly to the contracted UPS and generator paths with no shared single point of failure

    Before the suite is offered for tenant fit-out

    Redundancy re-verification record

    N+1 or 2N configuration at the shared plant level is unaffected by the new suite's load addition

    After each suite energisation

    Load bank commissioning report for the suite

    The suite's contracted kW capacity is delivered and held stable at the rack level

    Immediately prior to tenant SLA acceptance

    Environmental monitoring and alarm verification

    Temperature, humidity and leak detection points in the suite report correctly to the building management system

    Ahead of suite handover

    Level 5 integrated systems test extract for the shared plant

    The shared UPS, generator and cooling plant serving the suite were previously proven under integrated failure scenarios

    Referenced at each new suite acceptance

    SLA acceptance and witness pack

    The suite meets the tenant's contracted uptime and capacity commitments with the operator's evidence attached

    Final gate before the suite goes live

    How it runs

    From a proven base build to the next suite going live.

    Colocation is a continuous commissioning operation, not a single project — the register has to support that from day one.

    1. 01

      Commission the base build once

      Utility, generator, UPS, chiller and BMS subsystems proven through Level 4/5 and held as the shared reference.

    2. 02

      Model each suite as a subsystem

      Cages, pods and suites tagged against the base build systems they draw power and cooling from.

    3. 03

      Template the SLA record set

      Load bank, power quality, redundant feed and cooling capacity records defined once per suite type.

    4. 04

      Run acceptance per suite

      SLA testing executed and signed on tablet at go-live, referencing base build evidence rather than repeating it.

    5. 05

      Export a scoped dossier

      Per-tenant handover pack built from the suite's own records plus the base build dependencies it cites.

    FAQ

    Questions about Colocation facilities scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.