Chilled water, CDUs, direct-to-chip, rear-door

    Data center cooling commissioning software for halls where air and liquid cooling now share the same white space.

    AI-density racks put CDUs, direct-to-chip manifolds and rear-door heat exchangers alongside CRAH units, chillers and containment in the same hall. Deskely holds chilled water, air-side and liquid-side systems as linked subsystems, so a rack cannot be marked cooling-ready while the loop it depends on is unproven.

    Systems
    Chilled water, CRAH, CDU, RDHx
    Density driver
    AI racks and liquid loops
    Verification
    Airflow and containment
    Gate
    Rack-ready cooling capacity
    MECHANICAL PLANT ROOM — CHW LOOP 2MECHANICAL COMMISSIONING PACK · REV DCHILLER PLANTCHW PUMPSCHW SUPPLYCHW RETURNCRAH-10CRAH-11CRAH-12CDU-03CL01-CDU-03MANIFOLD FEEDING COLD PLATE LOOPSTAG REGISTERCDU-11Coolant distribution unit…Records signedCRAH-07Computer room air handler…In testCH-02Chiller 02PreservationCHWP-04Chilled water pump 04Punch open22 unitsunder one system hierarchy

    The problem

    Two cooling technologies, one hall, one commissioning gap.

    Chillers, CRAH/CRAC units, air containment and now CDUs and direct-to-chip manifolds are commissioned by different trades against different drawing sets, but they all feed the same racks.

    A rack is only cooling-ready once the plant, the air path and the liquid loop that serve it are all proven — a fact that spreadsheets rarely reconcile before racks are energised.

    Deskely models the chilled water plant, air-side distribution and liquid cooling loop as linked subsystems, so rack readiness is derived from all three rather than assumed from one.

    TWO TECHNOLOGIES, ONE UNPROVEN GAPAI-density hall — mixed coolingChilled water, air-side and liquid loop each commissioned by a different tradeChilled water plantSigned offCRAH air-side + containmentSigned offCDU / direct-to-chip loopPressure test openRack 118marked cooling-ready on plant + air only3 of 3loops actually required for that rackA rack is cooling-ready only when plant, air path and liquid loop all say so — not when the best-documented one does.Rack readiness is derived from all three linked subsystems, not assumed from one.

    Setting up the register

    Plant, air path and liquid loop are subsystems with explicit dependencies.

    Chillers, pumps, cooling towers, CRAH/CRAC units, containment aisles, CDUs, manifolds, quick-disconnects and rear-door heat exchangers are tagged assets under their own subsystem.

    Mechanical drawings, piping and instrumentation diagrams and rack elevations are parsed into the register, so a CDU's dependency on the technical cooling water loop is recorded rather than remembered.

    That structure is what lets a chiller plant complete its own commissioning while liquid cooling loops are still being pressure tested.

    1 · SOURCE DOCUMENTSMechanical P&IDs rev D48 sheetsCDU and manifold schedule22 unitsCRAH and air handler sch…38 unitsBMS sequence of operatio…212 sequencesPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERCDU-11Coolant distribution unit…LIQUID COOLINGCRAH-07Computer room air handler…AIR COOLINGCH-02Chiller 02PLANT ROOMCHWP-04Chilled water pump 04PLANT ROOMTWO DOCUMENTS DISAGREEMechanical P&IDs …Chiller 02CDU and manifold …Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Execution

    Flushing, pressure testing and airflow verification recorded at the loop and the aisle.

    Technicians capture flushing, fluid quality, pressure decay, leak testing and coolant distribution unit start-up on tablets at the equipment, including inside white space with hot aisle containment in place.

    Air-side commissioning — CRAH airflow balancing, containment integrity and hot/cold aisle differential verification — is recorded against the same aisle the liquid loop serves.

    Punch from a failed pressure test or an airflow imbalance is raised immediately and categorised by whether it blocks rack energisation.

    FLUSH, PRESSURE TEST, AIRFLOW, RACK-READYLiquid cooling loop L-06Flushing and fluid quality baseline100%Pressure decay and leak test100%CDU start-up and manifold connection72%CRAH airflow balancing, containment55%Rack-ready roll-up (plant + air + loop)20%20%racks fed by loop L-06 at rack-ready3linked subsystems feeding one statusA rack shows cooling-ready only once plant, air path and loop all report in.

    Cooling readiness

    A rack is cooling-ready when plant, air path and loop all say so.

    System readiness certificates for the chilled water plant, the air-side system and each liquid cooling loop feed a single rack-level readiness view, rather than three disconnected sign-offs.

    The cooling dossier per hall gives the operations team fluid quality baselines, airflow balancing results and CDU commissioning records from day one.

    Punch carried past energisation stays live with an owner, which matters when a liquid cooling loop is still being tuned during initial IT load.

    CHW loop 2 — cooling commissioning ladderHeat-load evidence gates full rated capacity acceptancePFCPre-functional checklistIssued 21 AprInstallation checks312 / 312 signedFlushing and water treatmentcompleteFTFunctional testReady — heat load bookedComponent tests closed88 / 88CDU leak testpassedHLTFull heat-load testBlocked — 5 itemsBlocking punch5 openN+1 chiller failovernot scheduled

    Liquid in a room built for air is a new failure mode

    A CDU leak isn't a punch item, it's a live-hazard event next to racks that were never designed to get wet.

    Rear-door heat exchangers and direct-to-chip loops put pressurised fluid a few centimetres from live IT equipment, in a room whose fire and electrical safety case was built around air cooling — which makes leak detection cabling, drip trays and automatic isolation valves as much a life-safety commissioning item as a mechanical one.

    Dielectric coolant loops raise a different question at commissioning: quick-disconnects have to be proven not to weep under repeated connect/disconnect cycles, since a CDU services multiple racks over its life and every reconnection is a fresh chance to introduce a leak path that wasn't there during initial pressure testing.

    Deskely records leak detection cable routing and zone coverage, drip tray placement and isolation valve response time as their own test set against each loop, distinct from the flushing and pressure decay records, because a facility can pass every hydraulic test and still have a blind spot in the row where a leak would actually be detected.

    FLUSHING, PRESSURE, AIRFLOW — AT THE LOOPCDU commissioning, Hall 2Recorded at the loop and the aisle it serves, with measured valuesLIQUID LOOP — CDU 08184 psipressure decay, 30 min hold0.02%fluid contamination, within specLeak test: no drop over hold periodAIR-SIDE — AISLE 4 CONTAINMENTCRAH airflow balancing vs designHot/cold aisle differential within bandContainment integrity, no bypass airGap found2 of 3loop and air checks passed cleanRack 118held from cooling-ready pending containment fixA rack is cooling-ready only once plant, air path and liquid loop each pass at the source.

    How it runs

    From chiller plant to a rack that can take load.

    Mixed air and liquid cooling is where data centre commissioning most often loses the dependency chain — Deskely is built to keep it.

    1. 01

      Model plant, air and liquid subsystems

      Chilled water plant, CRAH/CRAC air distribution and liquid cooling loops tagged as linked subsystems.

    2. 02

      Parse mechanical drawings

      P&IDs, rack elevations and CDU schedules drafted into a reviewed asset register.

    3. 03

      Record flushing and pressure testing

      Fluid quality, leak testing and pressure decay results captured per loop before energisation.

    4. 04

      Verify airflow and containment

      CRAH balancing, containment integrity and aisle differential recorded against each hall.

    5. 05

      Roll up to rack readiness

      Plant, air-side and liquid-side records combined into a single cooling-ready status per rack.

    6. 06

      Certify and hand over

      System readiness certificates issued from signed records, with the dossier exported to operations.

    FAQ

    Questions about Cooling and liquid cooling scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.