Overland conveyors, stackers, reclaimers, dust suppression

    Commissioning software for materials handling where a single idler failure on a fourteen-kilometre overland conveyor can stop the whole plant.

    A mine's materials handling circuit is a chain of conveyors, transfer towers, stackers and reclaimers strung across kilometres of open country, each drive, idler and belt scale depending on the one before it. Deskely tags every conveyor segment, transfer point and stacker/reclaimer as its own asset, so pre-functional checks, cold and hot commissioning and dust suppression testing are tracked end to end instead of vanishing into a single 'conveyor system' line item.

    Assets
    Conveyor, transfer tower, stacker/reclaimer
    Test
    Cold run, hot run, load trial
    Interface
    Belt scales, dust suppression, tripper cars
    Gate
    Mechanical completion by segment
    OVERLAND CONVEYOR — CV-201MATERIALS HANDLING RECORD SET · REV COVERLAND CONVEYOR CV-04 — 3.2 KMTRANSFER TOWER T3STACKERCV-04-BLTBelt tracking alarmTAG REGISTERCV-201Overland conveyor, drive …Records signedTT-02Transfer tower 2, chute l…In testBS-SPL-09Belt splice, chainage 3.2…PreservationMCC-CV2Motor control centre, dri…Punch open4,120 unitsunder one system hierarchy

    The problem

    A conveyor system is really dozens of assets and a spreadsheet cannot see which one is stalling ramp-up.

    An overland conveyor route is not one machine: it is drive pulleys, gearboxes, fluid couplings, hundreds of idler sets, belt scales, metal detectors, pull-cord and belt-drift switches, transfer chutes and dust suppression spray bars, all supplied and installed by different subcontractors on different weeks.

    Stackers and reclaimers add slew, luff and travel drives, boom conveyors and bucket-wheel or bridge-scraper mechanisms that need their own functional testing before they touch a stockpile, while the whole chain still has to cold-run empty before anyone risks a hot run under load.

    Deskely tags each conveyor segment, transfer tower and stockyard machine individually, so a construction manager can see exactly which idler run, chute liner or interlock is still open rather than being told the 'conveyor system' is 80% complete.

    A 'CONVEYOR SYSTEM' IS DOZENS OF ASSETSOverland route — 14 kmIdlers, scales, chutes and drives, each installed by a different subcontractorS1S2S3S4S5S6S7S8S9S10S11S12Segment = drive, idler run, belt scale, chute80%'conveyor system' reported complete2segments with an open idler or scale itemWHAT THE AVERAGE HIDESBelt scale calibration, S3openMetal detector sensitivity, S8openPull-cord switch coverageclosedDeskely tags each segment individually so ramp-up isn't blocked by an unnamed idler.

    Setting up the register

    Conveyor segments, transfer points and stockyard machines are structured to match how the belt actually runs.

    Each conveyor is broken into segments with its drive station, tail station, take-up, idler runs and belt scale as sub-tags, so a fault at chainage 4,200m is logged against that idler set and not against the conveyor as a whole.

    Transfer towers, chutes, tripper cars and dust suppression zones sit as their own subsystems with pre-functional checklists for liner wear points, spray nozzle coverage and access interlocks.

    Single line diagrams, mechanical GA drawings and vendor equipment lists are parsed into that structure, so the register mirrors the route survey rather than a generic conveyor checklist copied from the last project.

    1 · SOURCE DOCUMENTSConveyor general arrange…42 sheetsIdler and pulley schedule4,120 unitsDrive station schedule6 stationsBelt splice register18 splicesPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERCV-201Overland conveyor, drive …DRIVE STATIONTT-02Transfer tower 2, chute l…TRANSFER TOWERBS-SPL-09Belt splice, chainage 3.2…BELTLINEMCC-CV2Motor control centre, dri…ELECTRICALTWO DOCUMENTS DISAGREEConveyor general …Belt splice, chainage 3.2 kmIdler and pulley …Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Execution

    Cold run, hot run and load trial are gated in sequence, segment by segment.

    Pre-functional checks cover guarding, lubrication, belt tracking, pull-cord and drift switch operation and drive alignment before a segment is cleared for a no-load cold run.

    Hot commissioning under load brings in belt scale calibration, metal detector sensitivity testing, dust suppression spray verification and tripper car positioning, each captured against the specific asset rather than a blanket 'conveyor tested' checkbox.

    Vendor punch lists from the stacker/reclaimer OEM's commissioning engineer are logged at the specific drive or mechanism, so ramp-up is not blocked by an unrelated open item three transfer towers away.

    COLD RUN TO LOAD TRIAL, SEGMENT BY SEGMENTOverland route — segment S3Pre-functional checks — guarding, tracking100%No-load cold run100%Hot run under load75%Belt scale calibration and metal detection40%Mechanical completion by segment15%2 of 5gates cleared0gates skipped without evidenceEach segment runs its own ladder, so ramp-up starts on the sections that are ready.

    Ramp-up and handover

    Mechanical completion is issued by segment, so ramp-up can start on the sections that are actually ready.

    Mechanical completion and RFSU are issued per conveyor segment and stockyard machine from signed pre-functional and functional records, so ramp-up tonnage can begin on the ROM circuit while the overland route to the stockpile is still being hot-commissioned.

    Statutory inspection sign-off for guarding, emergency stops and pull-cord coverage is captured against the same asset register, satisfying the site's principal hazard management plan rather than a separate compliance binder.

    The handover pack for operations includes belt scale calibration certificates, dust suppression test results and vendor commissioning reports exported per segment, ready for the plant's condition monitoring team on day one.

    Drive station 1 — start-up ladderBelt start issues only from signed electrical test evidenceMIMechanical install completeRecords signed 21 JulIdler alignment records4,120 / 4,120 signedPulley lagging inspectioncompleteETElectrical and controls testIn test — electrical teamMotor no-load runconfirmedInterlock loop checks18 / 18CSConveyor start-upPunch open — 5 itemsBlocking punch5 openProject engineer sign-offnot witnessed

    Belt fire and spontaneous combustion detection

    A conveyor carrying sulphide concentrate or coal needs its fire detection and suppression system proven before it is trusted to run unattended overnight.

    Enclosed conveyor galleries and transfer towers handling sulphide concentrate, coal or other combustible fines carry linear heat detection cable, CO monitoring for early spontaneous combustion warning, and fixed or deluge suppression systems that are commissioned as a fire system, not a materials handling item, often by a specialist fire protection subcontractor working weeks after the mechanical belt commissioning is finished.

    A conveyor that has passed its cold run, hot run and load trial can still be unsafe to leave running unattended if the heat detection cable's zoning does not actually match the gallery it is meant to cover, or if the suppression deluge valve's response time was never timed against the fire panel's alarm output.

    Deskely tags the fire detection cable runs, CO monitoring points and suppression valves against the specific conveyor segment and gallery they protect, with functional test records — detection response time, suppression activation, fire panel zone mapping — held alongside the mechanical commissioning record, so unattended running approval is signed against a proven fire system rather than assumed because the belt itself runs cleanly.

    ONE CONVEYOR, TEN SEGMENTS, TEN OWNERSOverland route — 14 kmS1S2S3S4S5S6S7S8S9S10S4 belt scale calibration and S8 metal detector sensitivity are still openA SEGMENT = DRIVE, IDLER RUN, BELT SCALE, CHUTETen segments, each with its own commissioning path, not one blended completion figureDeskely tags every idler run and scale so a route's readiness is never a single average.

    How it runs

    From route survey to a belt that runs under load.

    Materials handling commissioning is won by tracking the chain link by link, not by waiting for one conveyor-wide sign-off that never quite arrives.

    1. 01

      Tag the route

      Every conveyor segment, transfer tower, chute and stockyard machine registered as its own asset with sub-tags for idlers, scales and interlocks.

    2. 02

      Run pre-functional checks

      Guarding, tracking, lubrication and switch checks captured per segment ahead of a no-load cold run.

    3. 03

      Hot commission under load

      Belt scale calibration, metal detection, dust suppression and stacker/reclaimer functional testing captured against the specific asset.

    4. 04

      Release segments for ramp-up

      Mechanical completion issued by segment so ramp-up tonnage starts on ready sections while the rest is still being proven.

    FAQ

    Questions about Materials handling and conveyors scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.