FPSO and floating production

    FPSO completions where the record travels with the module.

    Topsides in one yard, hull in another, integration in a third and hook-up offshore. Deskely keeps a package's history attached to the package itself, so what was tested at the fabricator is still provable after sail-away.

    Certification level
    Module and subsystem
    Locations
    Yard to offshore
    Parties
    EPC, yards, vendors
    Constraint
    POB and sail-away
    TOPSIDES MODULE M04 — SEPARATIONP&ID 21-002 · REV CHull — yard AM02M04M06M0821-V-101Turret and risersSUBSYSTEM 21-02 — MC AT YARDTAG REGISTER21-V-1011st stage separatorA-ITR signed21-LT-118Level transmitterB-ITR open21-C-210Stabiliser columnPreservation43-PU-204Hydrocyclone pumpPunch A open1 240 tagsunder one system hierarchy

    The problem

    The record is built in one country and audited in another.

    A topsides module is fabricated and tested at one yard, shipped to an integration yard, lifted onto a hull built somewhere else, then sailed to field and hooked up offshore. At each of those moves the scope changes hands, and traditionally so does the paperwork format.

    What gets lost in the moves is not usually the certificate. It is the layer beneath it: the calibration sheet from the vendor's works test, the punch item raised at the fabricator that quietly disappeared from the integration yard's list, the preservation cycles that lapsed during the tow.

    The offshore hook-up campaign then runs against a fixed number of berths and a limited weather window, and every hour spent re-verifying something already proven onshore is an hour not spent on the tie-in work that genuinely could not be done at the quayside.

    YARD SCOPE vs OFFSHORE CARRY-OVERTopsides — 6 modulesM01closedM02closedM03carriedM04closedM05carriedM06closedYard — quayside, full accessOffshore — beds, boats, weatherCLOSED BEFORE SAIL-AWAY1 240A and B records signed at the quayCARRIED OFFSHORE690re-tested with a marine spreadSAIL-AWAY DECIDED ON EVIDENCE, NOT OPINIONEvery carried item has an owner, a reason and a date.Carry-over register per moduleDeskely shows exactly what leaves the yard unfinished.

    Contract chain

    Six parties, one hull, and no single owner of the register.

    An FPSO scope splits cleanly along yard and vendor lines, and each party needs to work in its own lane without inheriting someone else's paperwork format.

    EPC / integrator

    Overall completions schedule and RFSU sequencing

    Signs

    Rolled-up module and subsystem readiness across all yards

    Topsides fabrication yard

    Module construction, static and loop testing

    Signs

    MC certificates and A/B ITRs per module before load-out

    Hull yard

    Marine systems, structural completion, ballast and mooring

    Signs

    Class-witnessed test records and hull MC packages

    Integration yard

    Module mating, interconnecting piping and cabling

    Signs

    Tie-in ITRs referencing both module registers

    Vendor package suppliers

    Skid-mounted equipment — compression, power generation, water treatment

    Signs

    Works test certificates carried forward into the project register

    Offshore commissioning team

    Hook-up, live commissioning, RFSU and first oil

    Signs

    C records, punch closure and PSSR evidence pack

    One register, many locations

    Scopes split by yard and vendor, records held in one place.

    Every party on an FPSO — the EPC, each yard, each vendor package supplier — needs to work on their own scope without seeing or editing everyone else's. That requirement is exactly why projects end up with four registers in the first place.

    In Deskely the split is done with access rights instead of files. A vendor completes and signs only the records for its own package; a fabrication yard sees only the modules it is building. Progress still rolls up into the project register with no import step, because there was never a separate file to import.

    So when a module leaves the yard, nothing has to be handed over. The module's tags, records, punch items and preservation history are already in the register the offshore team will use.

    How access control works
    1 · SOURCE DOCUMENTSP&ID 21-002 rev C1 240 tagsLine list rev B860 linesInstrument index412 loopsModule weight/tag report9 modulesPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTER21-V-1011st stage separator21-0221-LT-118Level transmitter21-0221-C-210Stabiliser column21-0343-PU-204Hydrocyclone pump43-01TWO DOCUMENTS DISAGREEP&ID 21-002 rev CLevel transmitterLine list rev BAbbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Certification ladder

    From module MC to first oil, each gate names its evidence.

    The same ladder recurs at module, subsystem and system level, which is why it has to be enforced by the data rather than tracked by memory.

    CERTIFICATION LADDER6 gatesMCModule MCA and B records signed, static testing complete, no openCategory A punchFabrication yard QC leadLORLoad-out releaseModule MC issued, preservation routines initiated, structuralsea-fastening verifiedYard marine warrantysurveyorIAIntegration acceptanceInterconnecting tie-in ITRs signed, module punch reconciledagainst fabricator listIntegration yardcompletions managerRFSURFSU (per subsystem)C records for the subsystem signed, Category A punch closed,preservation currentOffshore commissioningmanagerPSSRPSSRRFSU issued on all safety-critical subsystems, operatingprocedures reviewed, evidence pack exportedOperator PSSR chairFOFirst oilPSSR closed, process safety systems proven live, marine classendorsement currentOperator representativeEach gate is claimable only when the records beneath it are signed.
    1. 01

      Module MC

      A and B records signed, static testing complete, no open Category A punch

      Fabrication yard QC lead

    2. 02

      Load-out release

      Module MC issued, preservation routines initiated, structural sea-fastening verified

      Yard marine warranty surveyor

    3. 03

      Integration acceptance

      Interconnecting tie-in ITRs signed, module punch reconciled against fabricator list

      Integration yard completions manager

    4. 04

      RFSU (per subsystem)

      C records for the subsystem signed, Category A punch closed, preservation current

      Offshore commissioning manager

    5. 05

      PSSR

      RFSU issued on all safety-critical subsystems, operating procedures reviewed, evidence pack exported

      Operator PSSR chair

    6. 06

      First oil

      PSSR closed, process safety systems proven live, marine class endorsement current

      Operator representative

    Sail-away and hook-up

    Decide what sails with punch open, with the list in front of you.

    Sail-away is a judgement made under commercial pressure: which subsystems are genuinely complete, which can be finished offshore, and which items are being accepted as carry-over. That judgement is only as good as the punch list it is made against.

    Punch in Deskely is raised at the tag, with photographs, split by category and owned by a named party. Category A blocks the certificate above it outright. Category B is carried forward, still visible after sail-away, still assigned, and still counted in the offshore workload rather than forgotten in a closed-out spreadsheet.

    The offshore campaign is then planned against evidence: subsystems that already earned mechanical completion onshore are not re-walked, and the limited bed space is spent on hook-up, live testing and the punch that was always going to be offshore work.

    Punch list model
    CARRY-OVER ACROSS SAIL-AWAYYard week 148 → offshore hook-upSAIL-AWAYM01 Separation4% offshoreM04 Gas compression28% offshoreM07 Water injection45% offshoreM09 Flare and vent12% offshoreLiving quarters0% offshorecost of one ITR closed offshore1 940records deliberately carried overEvery carried item is a decision with a name and a date against it.Yard scope and offshore scope stay in one register, not two disconnected systems.

    What actually slips

    The failure modes are the moves, not the testing itself.

    None of these are technical problems. They are handover problems, which is exactly where a paper-and-spreadsheet process is weakest.

    SCHEDULE EXPOSURECONTROLLEDPunch item lost between yardsPunch stays attached to the tag across every yard move, withno re-entry step.Preservation lapses during towPreservation cycles run per tag on their own cadence and flagas overdue automatically, tow or no tow.Vendor test data never reaches the project…Vendor packages complete their own ITRs directly in the sharedregister under access control.Offshore re-testing to be safeSigned A/B records with signatory and timestamp travel withthe module, so re-testing is a choice, not a default.4 failure modes carried on the register, each with a named control.
    01

    Punch item lost between yards

    A Category B item raised at the fabricator does not reappear on the integration yard's list, and resurfaces offshore as a surprise.

    Punch stays attached to the tag across every yard move, with no re-entry step.

    02

    Preservation lapses during tow

    Rotating equipment and instrumentation sit idle for weeks during the sail from integration yard to field with no one routine covering the whole voyage.

    Preservation cycles run per tag on their own cadence and flag as overdue automatically, tow or no tow.

    03

    Vendor test data never reaches the project register

    A works test certificate is filed by the vendor and referenced by a document number that means nothing to the offshore team.

    Vendor packages complete their own ITRs directly in the shared register under access control.

    04

    Offshore re-testing to be safe

    Without confidence in the onshore record, the offshore team re-walks subsystems that were already proven, burning bed-days and weather window.

    Signed A/B records with signatory and timestamp travel with the module, so re-testing is a choice, not a default.

    Handover to operations

    The dossier assembles itself from the record that was already there.

    By first oil, an FPSO handover dossier has to reconcile records from four or five yards, dozens of vendor packages and an offshore campaign, into a single package the operator's asset team can rely on for the life of the field.

    Because every one of those records was signed against the same tag in the same register, the dossier is a filtered export rather than a reconstruction project. It carries the fabrication yard's works test, the integration yard's tie-in ITR and the offshore commissioning team's C record for that tag as one continuous chain.

    That continuity is what an insurer or a class society actually wants to see when a warranty question comes up years into operation: not a summary, but the original signed record from wherever it was created.

    Handover dossiers
    AUDIT QUERY21-LT-118Subsystem 21-02 · Instrument5 records returned · 0.4 sA-ITR 4.2Installation check (yard)T. Haugen — QC14 Mar 2026A-ITR 6.1Loop folder / calibrationM. Silva — Instr.02 Apr 2026PRES-Q3Preservation through towSystem log24 cyclesPUNCH1 Cat B carried offshoreAccepted by client11 May 2026B-ITR 2.4Loop test (offshore)J. Okafor — Comm.28 May 2026CERTIFICATEMC-21-02Mechanical completionIssued 04 Jun 2026Signed A. Reidar — OpsPrerequisites demonstratedOne record set from yard to offshore — nothing is re-keyed after sail-away.

    Typical scale

    The numbers behind a floating production project.

    3–5

    yards and integration sites

    fabrication, hull, integration and offshore

    40–80

    vendor package scopes

    each with its own works test record

    12–18 mo

    typical preservation duration

    from load-out to first oil

    6–10 wk

    offshore hook-up and commissioning window

    fixed by vessel and POB constraints

    How it runs

    How an FPSO scope is set up in Deskely.

    The organising principle is that the record belongs to the module, not to the location or the contractor currently holding it.

    1. 01

      Structure by module and subsystem

      Topsides modules, hull systems and marine systems are broken into subsystems that stay stable from fabrication through to offshore, so nothing has to be re-mapped after a move.

    2. 02

      Scope each party with access rights

      Yards, vendors and subcontractors are given edit and signature rights over their own packages only, while progress still rolls up to the project register.

    3. 03

      Capture vendor package records in place

      Works test results, calibration sheets and certificates from vendor packages are attached to the tags they belong to rather than filed as a separate document set.

    4. 04

      Run preservation through the tow

      Routines continue across yard moves and the transit, so the gap that normally appears during sail-away is visible if it happens and provable if it does not.

    5. 05

      Agree carry-over at sail-away

      Punch is reviewed by category with owners assigned, so what sails with open items is a decision on record rather than a discovery offshore.

    6. 06

      Close out offshore against evidence

      Hook-up and commissioning work from subsystems that already hold mechanical completion, and the handover dossier exports per subsystem as it is earned.

    FAQ

    Questions about FPSO scopes.