LNG and gas processing

    LNG commissioning, run per train instead of per plant.

    Liquefaction scopes carry the densest loop testing and the longest preservation windows in the industry, and the operator gates start-up one train at a time. Deskely keeps the records, the certification ladder and the readiness number at that same level.

    Certification level
    Per train
    Record density
    Loop and machine
    Preservation window
    24–36 months
    Operator gate
    PSSR
    TRAIN 2 — LIQUEFACTIONP&ID 52-118 · REV DFeed gas52-V-01452-K-101MR compressor52-E-201Cold box / MCHETT31858-TK-901LoadingTRAIN 2 — RFSU GATETAG REGISTER52-E-201Main cryogenic exchangerA-ITR signed52-TT-318Cold box temperatureB-ITR open52-K-101Mixed refrigerant compres…Preservation58-TK-901LNG storage tankPunch A open4 120 tagsunder one system hierarchy

    The problem

    A liquefaction train is not one commissioning scope. It is several thousand, gated in a fixed order.

    Pre-treatment, refrigeration, liquefaction, storage and loading each behave like their own project. Between them sit tens of thousands of instrument loops, hundreds of rotating machines and a utilities scope that has to be live long before any of them can be tested.

    The volume is only half of it. The compressor cannot be run before its lube oil system is commissioned, which cannot be commissioned before its instrument loops are proven, which cannot be proven before the loop's field devices are calibrated and installed. On a spreadsheet that dependency lives in somebody's head.

    When the operator asks whether train two can take feed gas, they are asking whether a specific list of subsystems has earned RFSU — and every one of those subsystems has to be provable on its own.

    TRAIN SEQUENCELiquefaction — 3 trainsConstructionPre-commCommRFSUTrain 1RFSU issuedHanded to operations4 120 tagsTrain 2Commissioning612 of 653 loops signed4 120 tagsTrain 3ConstructionMechanical completion open4 120 tagsPLANT-LEVEL PROGRESS REPORTED76%a figure that is true of no single trainStart-up gated per trainDeskely reports readiness at the level the operator actually gates.

    The certification ladder

    Four gates stand between steel and feed gas in the cold box.

    Each gate is issued at subsystem level, per train, and none of them are claimed on a status update.

    CERTIFICATION LADDER4 gatesMCMechanical completionAll A and B records signed, static tests complete, loop checksproven to the DCS marshalling cabinet.Construction manager andcommissioning leadRFSURFSUMC held, no open Category A punch, preservation current onevery tag in the subsystem.Commissioning manager,countersigned byoperationsPSSRPSSRRFSU on all subsystems feeding the train, safety-criticaldevices proof-tested, evidence pack exported.Operator PSSR panelFCFirst cargoLoading arm cryogenic and ESD interface tests, custody meterproving, tank gauging calibration.Terminal superintendentand buyer's surveyorEach gate is claimable only when the records beneath it are signed.
    1. 01

      Mechanical completion

      All A and B records signed, static tests complete, loop checks proven to the DCS marshalling cabinet.

      Construction manager and commissioning lead

    2. 02

      RFSU

      Enforced by the register, not reviewed against it afterwards.

      MC held, no open Category A punch, preservation current on every tag in the subsystem.

      Commissioning manager, countersigned by operations

    3. 03

      PSSR

      RFSU on all subsystems feeding the train, safety-critical devices proof-tested, evidence pack exported.

      Operator PSSR panel

    4. 04

      First cargo

      Loading arm cryogenic and ESD interface tests, custody meter proving, tank gauging calibration.

      Terminal superintendent and buyer's surveyor

    Setting up the register

    Loop and machine registers drafted from the drawing set, not typed from it.

    An LNG register is built from P&IDs, loop diagrams, line lists, cable schedules and vendor equipment lists — and on a two-train scope it is a year of senior engineering time if it is done by hand.

    Deskely's parser reads the document set and drafts the tag register, normalising tag formats and keeping the drawing reference behind each tag. Where a line list and a revised P&ID disagree, the conflict is shown side by side for an engineer to settle rather than silently picking one.

    Because the register is structured by system and subsystem from the start, the per-train breakdown the operator will gate against already exists before the first ITR is issued.

    See how the AI drawing parser works
    1 · SOURCE DOCUMENTSP&ID set 52-1xx rev D4 120 tagsCryogenic line list rev C2 380 linesInstrument index1 640 loopsMachine package registers38 packagesPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTER52-E-201Main cryogenic exchanger52-0452-TT-318Cold box temperature52-0452-K-101Mixed refrigerant compres…52-0258-TK-901LNG storage tank58-01TWO DOCUMENTS DISAGREEP&ID set 52-1xx r…Cold box temperatureCryogenic line li…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Preservation

    Cold boxes and compressors sit for years before they ever run.

    On a greenfield LNG project, main refrigerant compressors, pumps and motors are installed early and then wait — often two to three years — for the plant around them to be finished. Each needs its own routine the whole time: shaft rotation, nitrogen blanket pressure checks, insulation resistance, desiccant changes, lube oil sampling.

    Those routines run per tag and on their own cadence, independent of the commissioning sequence. An overdue cycle appears the day it is overdue rather than during a handover review, and each completed cycle carries the name, role and timestamp of whoever performed it.

    That record is what settles a warranty conversation with a machine vendor three years later: a filtered log of every cycle on that tag with signatures against it, not an assurance that preservation was maintained.

    How preservation works
    PRESERVATION LOGConstruction period — 36 months to first LNGM1M7M13M18M24TAG52-K-101Monthly — nitrogen blanket check52-K-102Monthly — shaft rotation52-E-201Quarterly — dew point sample52-TT-318Quarterly — dry gas purge58-P-4016-monthly — motor IR testBlanket lost — M10Re-purge signed, moisture retestedEvery cycle carries a signature, a date and the person who performed it — the record survives the whole build.

    Scale, in numbers

    What a two-train scope actually runs through the register.

    15,000–25,000

    instrument and machine tags per train

    24–36 mo

    typical rotating-equipment preservation window

    3–5

    distinct commissioning phases per train

    1

    readiness number per train, derived from records

    Who owns what

    Trains, jetty and utilities are usually different contracts.

    The register does not care who is contracted to whom; it cares which party owns which tag.

    EPC / lead contractor

    Process trains, utilities, mechanical completion and RFSU submission

    Signs

    A/B/C records, MC and RFSU certificates

    Rotating equipment vendors

    Compressor and turbine works tests, site acceptance

    Signs

    Vendor test certificates, run logs

    Marine / jetty contractor

    Loading arms, custody metering, ship–shore ESD link

    Signs

    Cryogenic and interface test records

    Operator commissioning team

    PSSR, hydrocarbon introduction approval

    Signs

    Reviewed evidence pack, PSSR minutes

    Preservation crew

    Idle-equipment routines from installation to start-up

    Signs

    Signed preservation cycle logs per tag

    Terminal / buyer surveyor

    First cargo acceptance

    Signs

    Meter proving and loading arm certificates

    What a train's dossier actually holds

    The records the operator opens before hydrocarbon reaches the cold box.

    An LNG train is accepted on a specific set of witnessed results, not on a general assurance that testing took place. Each one is produced by a named party at a fixed point in the sequence and stays attached to the tag it belongs to.

    RECORDS PRODUCED6 typesCryogenic leak test recordDuring cold commissioning of the…Cold box dry-out and purge logImmediately ahead of first cool-downCustody metering proving…Before first cargoLoading arm ESD interface testDuring jetty commissioning, re-verified…Compressor string test reportAt the vendor works, ahead of site…Boil-off gas system commissioning…During storage and loading system…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Cryogenic leak test record

    Piping and joints hold integrity at liquefaction temperature before feed gas is introduced

    During cold commissioning of the affected train

    Cold box dry-out and purge log

    Moisture and air have been removed from the main cryogenic heat exchanger before start-up

    Immediately ahead of first cool-down

    Custody metering proving certificate

    The export meter factor and uncertainty are accepted before commercial loading begins

    Before first cargo

    Loading arm ESD interface test

    The arm disconnects safely on a ship-shore emergency shutdown signal

    During jetty commissioning, re-verified before first cargo

    Compressor string test report

    The main refrigerant compressor train performs to design across its operating envelope

    At the vendor works, ahead of site installation

    Boil-off gas system commissioning record

    Vapour recovery and re-liquefaction respond correctly to tank pressure

    During storage and loading system commissioning

    Jetty, cargo and commercial acceptance

    First cargo is a commercial event, and the loading arms, meters and ship–shore link have to be proven before the carrier arrives.

    Liquefaction gets the attention, but the export jetty is where an LNG project actually earns money: cryogenic loading arms, custody transfer metering, tank gauging, boil-off gas handling and the ship–shore emergency shutdown link all have to be tested, witnessed and signed before a carrier is accepted alongside.

    These systems are usually built by a different contractor on a different schedule, and their records tend to live in a separate marine package. When first cargo slips, it is often because a metering certificate or an ESD interface test that nobody was tracking turns out to be missing.

    Deskely holds the jetty, the arms, the metering skid and the tank gauging system in the same register as the liquefaction trains, so first cargo readiness is one status, and the buyer's and terminal's evidence requirements are an export rather than a search.

    JETTY AND FIRST CARGOLoading arms · custody meteringLA-01 to LA-04 — cryogenic proving, ESD-1 and ESD-2 trip testsCarrier alongsideCARGO CUSTODY EVIDENCETank gauging system calibrationCustody transfer meter provingShip–shore link and ESD interface testOpenBoil-off gas handling proven at rateCargo tank cool-down rate recordOpen2items between here and first cargo1evidence set for buyer and terminalCommercial acceptance of the first cargo rests on records, not on a good day at the jetty.

    Terminology on this scope

    Words this page uses the way an LNG project actually uses them.

    RFSU
    Ready for start-up: a subsystem has been commissioned and is safe to take process feed.
    Cold box
    The insulated structure housing the main cryogenic heat exchanger where natural gas is liquefied.
    Boil-off gas (BOG)
    Gas that vaporises from stored LNG due to heat ingress, handled by dedicated compression and recovery systems.
    Custody transfer metering
    The metering skid whose calibration and proving certificates set the commercial quantity of LNG sold.
    Ship–shore link
    The emergency shutdown and communication interface between the jetty and the LNG carrier during loading.
    PSSR
    Pre-start-up safety review: the operator's final gate before hydrocarbon is introduced to a train.
    Preservation routine
    A scheduled maintenance cycle protecting idle equipment between installation and commissioning.

    How it runs

    How an LNG scope is set up in Deskely.

    The structure is decided once, at the start, and then everything else is a consequence of it. Getting the train and subsystem breakdown right is most of the work.

    1. 01

      Break down by train and utility

      Systems and subsystems are created per train, with shared utilities held separately so a common scope does not block a single train's certification.

    2. 02

      Draft the register from drawings

      P&IDs, loop diagrams and equipment lists are parsed into a tag register with drawing references retained, then reviewed and corrected by a completions engineer.

    3. 03

      Assign ITR templates by tag type

      Loops, valves, machines and vessels each get their A, B and C record templates, so a twenty thousand tag scope is populated without building forms one by one.

    4. 04

      Start preservation at installation

      Routines and cadences are attached to rotating equipment and instruments as they are installed, running in parallel with construction for as long as the wait lasts.

    5. 05

      Run field capture on tablets

      A, B and C records are completed at the tag, offline where necessary, with photos and signatures that keep the time they were taken.

    6. 06

      Gate MC and RFSU per subsystem

      Certificates issue only when the records beneath them allow it, and each train's readiness number is derived from those certificates rather than reported alongside them.

    FAQ

    Questions about LNG scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.