Refineries and petrochemical

    New build beside live plant, documented to the operator's standard.

    Refinery and petrochemical scopes have two customers: the project that has to finish, and the operating organisation that keeps the records for the life of the unit. Deskely produces evidence that satisfies both, including the pre-start-up safety review.

    Certification level
    Per unit
    Environment
    Live and brownfield
    Operator gate
    PSSR
    Retention
    Life of asset
    UNIT 24 — CRUDE DISTILLATION REVAMPP&ID 24-088 · REV FUnit 22 — liveBATTERY LIMIT24-F-001Crude heater24-C-101Atmospheric columnPSV318SCENaphthaKeroseneDiesel24-E-20424-PU-402AUNIT 24 REVAMP — PSSR SCOPETAG REGISTER24-C-101Atmospheric columnA-ITR signed24-PSV-318Column relief valveB-ITR open24-E-204Preheat train exchangerPreservation24-F-001Crude heaterPunch A open2 640 tagsunder one system hierarchy

    The problem

    The project finishes. The records stay for thirty years.

    A refinery unit is commissioned once and operated for decades. The people who will rely on the commissioning record — process safety, inspection, maintenance planning — are not in the room when the documentation format is decided, and they are the ones who pay for it later.

    Meanwhile the project has its own pressures: new equipment tying into live units, permits and isolations shared with operations, and a start-up date sold to a refinery economics model.

    The friction shows at the pre-start-up safety review. The operating organisation asks for evidence in their structure, the contractor has it in theirs, and several weeks are spent converting one into the other while the unit sits ready.

    TWO CUSTOMERS FOR THE SAME RECORDUnit 24 revampPROJECTfinishes and leavesOPERATIONSkeeps it for the life of the unitBATTERY LIMITITR packProject numberingPlant asset numberWeld and NDTFabricator filesIntegrity registerLoop testsCommissioning logControl system masterPunch listClosed at hand-overCarried for yearsPRE-START-UP SAFETY REVIEWBoth sets of evidence are read in the same meeting.Exported in the operator's structureDeskely writes once and satisfies both organisations.

    What the project is actually up against

    The standards and constraints that shape a brownfield refinery scope.

    Isolation authority
    Shared with live-plant operations
    Permit-to-work issued by the site, not the project
    Tag numbering
    Operator's existing scheme retained
    Safety review
    PSSR against API RP 750 / OSHA PSM-style criteria
    Retention
    Life of asset, typically 25–30 years
    Commissioning passes
    Cold then hot, separated by PSSR

    Setting up the register

    Units and subsystems that match how the plant is actually operated.

    The breakdown follows operating reality: process units, utilities, offsites and tank farm, each split into subsystems that can be commissioned and handed over independently. Shared utilities are held separately so a common scope does not hold a unit hostage.

    The tag register is drafted from the drawing package — P&IDs, line lists, instrument index, electrical schedules — with the source drawing kept behind each tag. On a brownfield scope the existing plant tag numbering is preserved, because the operating organisation will not renumber their asset to suit a project.

    That single decision, made at setup, is what makes the eventual dossier usable by the people who inherit it.

    See how the AI drawing parser works
    1 · SOURCE DOCUMENTSP&ID set 24-0xx rev F2 640 tagsLine list rev D1 480 linesOperator CMMS extract5 240 assetsSCE / safety-critical re…218 elementsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTER24-C-101Atmospheric column24-0624-PSV-318Column relief valve24-0624-E-204Preheat train exchanger24-0424-F-001Crude heater24-02TWO DOCUMENTS DISAGREEP&ID set 24-0xx r…Column relief valveLine list rev DAbbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    What actually blows the schedule

    Four failure modes specific to new build beside a running unit.

    SCHEDULE EXPOSURECONTROLLEDIsolation certificate expires mid-testIsolation certificates and their expiry are tracked againstthe ITRs they gate, so a lapsing permit is visible before it…Brownfield tag renumbered by the projectThe plant's existing tag numbering is enforced at registersetup and never overwritten downstream.PSSR evidence assembled from scratchSafety-critical tags are flagged at setup and filtered as asingle evidence view exportable on demand.Cold-phase punch lost at cut-inPunch stays attached to the tag through hot commissioning;Category A blocks the certificate above it regardless of…4 failure modes carried on the register, each with a named control.
    01

    Isolation certificate expires mid-test

    A tie-in test outruns the permit window shared with operations, and work stops while a new isolation is authorised.

    Isolation certificates and their expiry are tracked against the ITRs they gate, so a lapsing permit is visible before it blocks the crew.

    02

    Brownfield tag renumbered by the project

    A contractor issues new tag numbers for convenience, and the operator's CMMS can no longer match records to its own asset register.

    The plant's existing tag numbering is enforced at register setup and never overwritten downstream.

    03

    PSSR evidence assembled from scratch

    Safety-critical records — relief devices, trips, fire and gas — are scattered across contractor files and take weeks to compile for the review.

    Safety-critical tags are flagged at setup and filtered as a single evidence view exportable on demand.

    04

    Cold-phase punch lost at cut-in

    Punch items raised during chemical cleaning and steam blows are closed administratively rather than physically before feed is introduced.

    Punch stays attached to the tag through hot commissioning; Category A blocks the certificate above it regardless of phase.

    Cold commissioning and hot commissioning

    A refinery unit is commissioned twice, once with no hydrocarbon in it and once with feed running through it.

    Cold commissioning is chemical cleaning, steam blows, air blowing and reinstatement, loop checks and trip testing, catalyst loading under inert gas and machinery solo runs. Hot commissioning is feed cut-in, furnace light-off, establishing reflux, getting on-spec product to rundown and the witnessed guarantee run.

    The pre-start-up safety review sits between the two, and it is the point at which project evidence has to convince operations, HSE and often an insurer that the unit is safe to take feed.

    Because both phases run against one register, the tag tested on air is the tag that runs on feed: trip test results stay attached through the cut-in, cold-phase punch stays visible during the ramp, and performance test data lands in the same dossier the maintenance team inherits.

    COLD COMMISSIONING → HOT COMMISSIONINGWhere the record set changes handsCOLD — NO HYDROCARBONChemical cleaning and flushingSteam blows on the main headersAir blowing and reinstatementLoop checks and trip testingCatalyst loading under inert gasMachinery solo runs on airHOT — FEED INFeed cut-in and unit line-upFurnace light-off and rampReflux established on the columnOn-spec product to rundownPerformance test runGuarantee run witnessedPSSRONE REGISTER SPANS BOTH SIDESThe tag tested on air is the tag that runs on feedTrip test results stay attached through the feed cut-inPunch raised in cold commissioning is visible during the rampPerformance test data lands in the same dossier as the ITRsOperations accepts the unit from evidence, then keeps using it for maintenance.Nothing is re-typed at the boundary between construction and production.

    What the review reads

    The records a PSSR panel actually opens, and when they are created.

    RECORDS PRODUCED5 typesRelief device proof testDuring cold commissioning, re-verified…Trip and interlock functional testLoop checks through cold commissioningIsolation and permit historyContinuously, at each tie-inCold commissioning punch statusReviewed immediately before PSSRGuarantee run performance dataDuring hot commissioning, post-PSSRDOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Relief device proof test

    Overpressure protection is set and functional before feed

    During cold commissioning, re-verified pre-PSSR

    Trip and interlock functional test

    Safety instrumented functions respond within spec

    Loop checks through cold commissioning

    Isolation and permit history

    Tie-ins were executed under authorised, closed-out permits

    Continuously, at each tie-in

    Cold commissioning punch status

    No Category A items remain open ahead of hydrocarbon-in

    Reviewed immediately before PSSR

    Guarantee run performance data

    The unit meets contractual throughput and product spec

    During hot commissioning, post-PSSR

    Handover

    A dossier the site can still use in ten years.

    The handover package exports per unit and per subsystem in the structure the operating organisation retains, with certificates, signed records, punch position and preservation history under the tags the plant actually uses.

    Category B items that will be closed during normal operations are carried with an owner and a date, which is what makes the outstanding list credible to the maintenance planner receiving it rather than something quietly written off at handover.

    Because the dossier is exported from the live register, the operating organisation can be given a package for a subsystem the week it is complete, instead of everything arriving as one archive months after start-up.

    AUDIT QUERY24-PSV-318Subsystem 24-06 · Safety-critical element5 records returned · 0.3 sA-ITR 4.2Installation and orientationT. Haugen — QC12 Feb 2026PSV-BSBench set certificateValve workshop28 Feb 2026PRES-Q1Preservation historySystem log9 cyclesPUNCH1 Cat B carriedAccepted by operator14 Apr 2026B-ITR 5.1Function test witnessedJ. Okafor — Comm.21 May 2026CERTIFICATEMC-24-06Mechanical completionIssued 29 May 2026Signed A. Reidar — OpsPrerequisites demonstratedThe operator receives the dossier in their own tag numbering, ready to load into the refinery CMMS.

    Scale, in numbers

    What a brownfield unit tie-in typically runs through the register.

    8–15

    tie-in points per unit revamp

    2 passes

    cold then hot commissioning, split by PSSR

    25–30 yr

    typical record retention on the operator's side

    1

    tag numbering scheme, kept from project through operations

    How it runs

    How a refinery scope is set up in Deskely.

    The structure is chosen for the people who will keep the records, not for the convenience of the project that produces them.

    1. 01

      Break down by unit and utility

      Process units, utilities, offsites and tank farm become systems and subsystems that can be certified and handed over independently.

    2. 02

      Keep the operator's tag numbering

      Existing plant tags are preserved on brownfield scopes so the dossier remains usable by maintenance and inspection after the project leaves.

    3. 03

      Draft the register from drawings

      P&IDs, line lists and the instrument index are parsed into a tag register with drawing references retained for engineer review.

    4. 04

      Flag safety-critical elements

      Relief devices, trips, interlocks and fire and gas tags are marked so their records can be filtered as one view for the safety review.

    5. 05

      Commission against live-plant constraints

      Tie-in and isolation scopes are executed on tablets at the tag with offline capture, so records exist the day the work is done.

    6. 06

      Certify per unit and export for PSSR

      RFSU is gated on the records beneath it, and the evidence pack exports per unit in the operator's retention structure.

    FAQ

    Questions about Refineries scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.