GT, HRSG, ST, first fire to first sync

    Commissioning software for a combined cycle plant where steam blows and first synchronisation are gates, not milestones on a chart.

    A combined cycle plant is three power islands — gas turbine, HRSG and steam turbine — that only earn revenue once every subsystem is chemically clean, steam-blown and proven to the grid. Deskely holds mechanical, electrical, I&C and process subsystems in one register, so first fire, first synchronisation and reliability run are issued from signed evidence rather than assembled the night before.

    Islands
    GT, HRSG, ST, BOP
    Sequence
    Clean, blow, fire, sync
    Gate
    Grid code compliance
    Output
    PAC and reliability run
    BLOCK 1 — GT/ST/HRSG TRAINP&ID SET 10-2xx · REV EGT-01HRSG-01ST-01CONDENSERSTACKHRSG-01-DRM1duct burner openCCGT BLOCK 1 — GT / HRSG / ST TRAINTAG REGISTERGT-01Gas turbine generator setRecords signedHRSG-1-SH2Superheater 2 outlet head…In testST-01Steam turbine generatorPreservationFDR-1211kV auxiliary feederPunch open18 packagesunder one system hierarchy

    The problem

    The steam blow package alone can carry hundreds of temporary supports and target plates.

    Chemical cleaning, steam blows, boil-out and target plate inspections are logged by different disciplines at different times, and a single missed cycle can force a re-blow weeks later when the schedule has already moved on.

    First fire and first synchronisation each depend on dozens of prerequisite systems being mechanically complete, loop-checked and protection-tested — a dependency map that lives in someone's head is discovered wrong at the worst possible moment.

    Deskely models every subsystem with its prerequisites explicit, so the readiness for first fire or first sync is a status the system reports, not a meeting the project manager convenes.

    RE-BLOW RISK ON A MOVING SCHEDULEHRSG steam blow packageTarget plate pit counts decide whether the blow is accepted or repeatedTP-01pit count within limitTP-02pit count within limitTP-03pitting exceeds limit — re-blow requiredTP-04pit count within limitTP-05pitting exceeds limit — re-blow requiredWHAT A RE-BLOW COSTS DOWNSTREAMHRSG re-opened, temporary supports re-erectedFirst fire slot lost — dependent systems re-sequencedFirst synchronisation moves behind the network outage window2 of 5target plates forcing a re-blow1first-sync slot at riskDeskely gates first fire and first sync on the same prerequisite subsystems, automatically.

    Setting up the register

    GT, HRSG, ST and balance of plant are subsystems with their own turnover packages.

    The plant is broken into systems and subsystems: gas turbine and enclosure, generator and excitation, HRSG pressure parts and ducting, steam turbine and condenser, cooling water, fuel gas, DCS and protection.

    P&IDs, single line diagrams and equipment lists are parsed into a reviewed tag register, so every valve, instrument and electrical device carries its drawing reference from day one.

    System turnover packages are built subsystem by subsystem, which is what allows the HRSG to be steam-blown while the ST bay is still being wired.

    1 · SOURCE DOCUMENTSP&ID set 10-2xx rev E2 340 tagsGT/ST vendor package reg…18 packagesHRSG piping isometrics640 linesI/O and cause-and-effect…6 800 pointsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERGT-01Gas turbine generator setBLOCK 1HRSG-1-SH2Superheater 2 outlet head…HRSG-1ST-01Steam turbine generatorBLOCK 1FDR-1211kV auxiliary feederELECTRICALTWO DOCUMENTS DISAGREEP&ID set 10-2xx r…Superheater 2 outlet headerGT/ST vendor pack…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Chemical cleaning and steam blows

    Cleanliness targets and blow efficiency are recorded evidence, not a verbal sign-off.

    Chemical cleaning circuits, flush sequences, passivation and boil-out results are captured against the piping subsystem, with target plate photographs and pit counts attached where required.

    Steam blow records hold pressure, temperature, target plate condition and blow count, and the subsystem stays open until the acceptance criteria are met and signed.

    Because the record set is templated per subsystem type, a repeated blow is a new instance of the same record rather than a fresh document to draft under pressure.

    STEAM BLOW TO FIRST SYNCHRONISATIONCombined cycle gate ladderChemical cleaning and boil-outSigned offSteam blow acceptance, all target platesSigned offFuel gas, cooling water, DCS loop-checkedIn progressFirst fireAwaiting predecessorGrid code compliance testingAwaiting predecessorFirst synchronisationAwaiting predecessor3of 6 gates cleared0re-blows currently openFirst synchronisation cannot open until grid compliance evidence sits behind it.

    First fire and first synchronisation

    The GT lights and the plant synchronises only once every prerequisite subsystem is signed.

    First fire depends on fuel gas systems, protection relay settings, cooling water and the DCS being commissioned and loop-checked; first synchronisation depends on that plus grid code compliance testing and protection coordination with the transmission or distribution operator.

    Deskely gates the first fire and first sync certificates on those prerequisites, so a subsystem left incomplete blocks the certificate automatically rather than relying on someone remembering to check.

    Grid code compliance tests — voltage ride-through, frequency response, reactive power capability — are recorded against the interconnection subsystem with the results the network operator will ask to see.

    Block 1 — synchronisation ladderEach certificate issues only from signed records beneath itMCMechanical completionIssued 14 MarPunch list Cat A0 openPiping hydro testscompleteFFFirst fireReady — hold point bookedFuel gas skid provencompletePermissive matrix signed24 / 24SYNCGrid synchronisationBlocked — HRSG steam blow openSteam blow cleanlinessnot achievedProtection settings appliedpending

    PAC, FAC and the reliability run

    The reliability run is the last gate, and trips during it are evidence, not excuses.

    Provisional and final acceptance depend on a reliability run at load with a defined trip-free window, and any trip during the run resets the clock against a documented cause.

    Deskely tracks the run period, logs interruptions against the subsystem responsible, and issues PAC and FAC certificates from the same signed record set used throughout commissioning.

    The completed dossier — cleaning, blows, loop checks, protection settings, grid compliance, reliability run — is exported to the owner as one pack rather than reconstructed from six contractors' files.

    AUDIT QUERYHRSG-1-SH2Block 1 · HRSG-1 · superheater 2Full history retrieved in one queryINSTPiping installationHRSG contractor08 FebNDTWeld NDT releaseInspection engineer16 FebBLOWSteam blow recordCommissioning engineer02 MarFUNCTemperature loop checkControls engineer10 MarCERTIFICATEMCMechanical completion14 MarOwner's engineerPrerequisites demonstratedThe synchronisation dossier exports per train on the day the block is handed over.

    Grid support and black start capability

    A combined cycle plant is dispatched to keep the grid alive, and governor droop, load rejection and black start tests prove that before the TSO trusts it in an emergency.

    Beyond first synchronisation, a grid-critical CCGT has to prove it can be relied on when the system is stressed: governor droop and primary frequency response tests, full and partial load rejection without tripping, and — where the connection agreement requires it — a black start sequence that brings the plant up from a dead grid on its own diesel generators and battery systems.

    These tests are usually scheduled once, late in commissioning, on a plant the operator is already under pressure to declare commercially available, and a failed load rejection test can mean re-tuning the governor and steam bypass system and repeating the whole sequence days later.

    Deskely holds load rejection, droop response and black start test records against the same subsystem tags used throughout commissioning, so a repeated test is a new dated instance rather than a document overwritten under schedule pressure, and the TSO's witness sees the full attempt history, not just the pass.

    GRID CODE COMPLIANCE DOSSIERInterconnection subsystemCOMPLIANCE TEST RESULTSVoltage ride-through0% for 140 msFrequency responsewithin envelopeReactive power capability±0.30 pfProtection coordination with TSOunder reviewFIRST SYNC PREREQUISITESFuel gas system commissionedProtection relay settings signedCooling water and DCS loop-checked3 of 4compliance tests signed1dossier sent to the network operatorFirst synchronisation reads from the same signed compliance evidence, not a summary claim.

    What reliability sign-off reads

    The records a grid operator and an insurer both want to see before a combined-cycle unit is declared commercial.

    A combined-cycle plant proves itself across three distinct machines and a grid interface, on a schedule where a missed steam blow criterion can push first fire by weeks. The dossier keeps turbine, boiler and grid records under one tag set so commercial operation is argued from evidence, not a punch list.

    RECORDS PRODUCED6 typesGas turbine first-fire and…During gas turbine commissioning, ahead…Steam blow completion recordBefore HRSG-to-steam-turbine tie-inGrid code compliance witness testPre-synchronisation, witnessed by the…HRSG hydrostatic and chemical…Pre-commissioning, before first steamReliability run and trip-free…During the performance and reliability…Capacity and heat rate performance…At the guarantee test, after reliability…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Gas turbine first-fire and start-up log

    Combustion, exhaust temperature spread and vibration are within OEM limits at ignition

    During gas turbine commissioning, ahead of steam raising

    Steam blow completion record

    Piping is clean to the target cleanliness before steam is admitted to the turbine

    Before HRSG-to-steam-turbine tie-in

    Grid code compliance witness test

    The unit's voltage, frequency and fault-ride-through response meets the connection agreement

    Pre-synchronisation, witnessed by the network operator

    HRSG hydrostatic and chemical clean certificate

    Pressure boundary integrity and internal cleanliness meet the design code before firing

    Pre-commissioning, before first steam

    Reliability run and trip-free operation record

    The unit sustains rated load without an unplanned trip over the contractual test window

    During the performance and reliability test, ahead of commercial operation

    Capacity and heat rate performance test report

    Output and fuel efficiency meet the contracted guarantee figures

    At the guarantee test, after reliability run completion

    How it runs

    From chemical cleaning to a trip-free reliability run.

    Combined cycle projects reward a subsystem structure agreed before construction finishes, because first fire and first synchronisation arrive fast once mechanical work is done.

    1. 01

      Break the plant into subsystems

      GT, HRSG, ST, generator, fuel gas, cooling water, DCS and protection, each with its own turnover package.

    2. 02

      Parse the tag register

      P&IDs, single lines and equipment lists drafted into a reviewed register with prerequisites mapped between subsystems.

    3. 03

      Run cleaning and steam blows

      Chemical cleaning, boil-out and steam blow records captured against the piping subsystem, with target plate evidence attached.

    4. 04

      Loop-check and protection-test

      I&C loop checks and protection relay settings signed per device before the subsystem is offered for energisation.

    5. 05

      Gate first fire and first sync

      Certificates issued only once fuel gas, cooling water, DCS and grid compliance prerequisites are signed.

    6. 06

      Track the reliability run

      Run period, trips and causes logged against the responsible subsystem, PAC and FAC issued from the record set.

    FAQ

    Questions about Gas and combined cycle scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.