AIS, GIS, protection and control

    Substation commissioning software for programmes where energisation depends on a TSO witnessing the right test.

    A substation build stacks primary plant, protection and control panels, SCADA and a TSO or DNO witness programme on top of each other, and none of it can be energised out of order. Deskely holds bays, panels and points in one register with the injection tests, witness points and sign-offs that actually gate the switch.

    Plant
    AIS and GIS bays
    Panels
    Protection and control
    Tests
    Primary and secondary injection
    Gate
    TSO or DNO witness and energise
    SUBSTATION — 132/33kVPROTECTION RECORD SET · REV CBUS 1RELAY 1BAY-01RELAY 2BAY-02RELAY 3BAY-03SS-BKR-02protection test openSUBSTATION SINGLE LINE — BUS 1, 3 BAYSTAG REGISTERBAY-2AFeeder bay 2A, 132kVRecords signedBAY-2A-REL-01Distance protection relayIn testCB-2ACircuit breaker, bay 2APreservationFDR-1233kV outgoing feeder 12Punch open48 relaysunder one system hierarchy

    The problem

    Every bay has its own panel, and every panel has its own paper trail.

    A transmission substation might carry twenty bays, each with primary plant, a protection and control panel, a SCADA gateway and a set of interlocks — and the network operator's witness list does not match any single contractor's paperwork.

    Injection test results, relay settings and SCADA point checks arrive as separate PDFs from separate parties, and the energisation meeting spends its time reconciling them rather than deciding.

    Deskely holds every bay, panel and point in one register with the tests that gate energisation modelled explicitly, so the switching request is backed by evidence rather than assurances.

    TWENTY BAYS, TWENTY PAPER TRAILSWitness list vs contractor packsBay 04 — 132 kV feederProtection contractor PDFnot on TSO's listBay 07 — bus couplerPrimary plant vendor reportnot on TSO's listBay 11 — transformer feederSCADA integrator lognot on TSO's listBay 14 — reactive compensationCivil handover notenot on TSO's listWHAT THE ENERGISATION MEETING SPENDS ITS TIME ONReconciling four separate PDFs against one witness listDeciding, not just checking, because nobody trusts the paperwork4paper trails for one energisation date1register the TSO actually needsDeskely flags TSO witness points in the register, so the right tests are visible in advance.

    Setting up the register

    Bays, panels and SCADA points are structured with the interlocks between them.

    Single line diagrams, protection schematics, cable schedules and SCADA point lists are parsed into a reviewed register, with each bay holding its primary plant, CTs and VTs, protection relays and control panel.

    SF6 handling — filling, moisture and leak records for GIS bays — sits against the specific gas compartment, not a general project log.

    Interlocks and permissives between bays are modelled explicitly, so a bay cannot be marked ready for energisation while a dependency it relies on is still open.

    1 · SOURCE DOCUMENTSSingle line diagram rev C6 baysProtection relay schedule48 relaysPrimary injection test p…6 baysSCADA point list2 180 pointsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERBAY-2AFeeder bay 2A, 132kVBAY 2ABAY-2A-REL-01Distance protection relayBAY 2ACB-2ACircuit breaker, bay 2ABAY 2AFDR-1233kV outgoing feeder 12BAY 4TWO DOCUMENTS DISAGREESingle line diagr…Distance protection relayProtection relay …Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Execution

    Injection testing and point checks are captured against the relay and the point, not a folder.

    Protection engineers record primary injection and secondary injection results — pickup, timing, CT ratio and polarity checks — directly against the relay under test, with test set details and ambient conditions kept as part of the record.

    SCADA points are checked end to end, from field device through RTU to control room indication, ticked off point by point rather than reported as a percentage.

    Punch raised during commissioning is categorised by whether it blocks energisation, a bay handover, or can be carried, so the witness meeting works from a filtered list.

    INJECTION TEST TO TSO WITNESSBay 11 · 132 kV feederPrimary and secondary injection — relay under testSigned offSCADA point-to-point verificationSigned offInterlock and permissive checksIn progressTSO witness point — flagged tests onlyAwaiting predecessorEnergisation certificateAwaiting predecessor20bays feeding one witness list0tests witnessed twice by mistakeThe TSO's engineer sees only the tests flagged for their witness, not the full history.

    Witness and energisation

    Energisation is authorised from the record set the network operator actually asked for.

    TSO or DNO witness points are flagged in the register in advance, so the operator's engineer sees exactly the tests that require their sign-off, not the whole commissioning history.

    The energisation certificate is issued once protection settings, injection results, interlock checks and SCADA verification are signed, with any carried punch listed against an owner.

    The bay dossier — settings, test results, SF6 records and drawings — is exported at handover, which is what the operations team needs from day one of live service.

    Bay 2A — energisation ladderEach certificate issues only from signed records beneath itPPTPrimary plant testIssued 22 AprCircuit breaker mechanism testcompleteInsulation resistance testcompletePROTProtection commissioningReady — primary injection bookedRelay settings applied6 / 6 relaysCT/VT ratio testscompleteENBay energisationBlocked — 4 itemsPrimary injection testnot completedBlocking punch4 open

    Busbar protection, CT ratios and revenue metering

    A busbar protection scheme has to be right the first time, and the CT ratios behind the revenue meter matter as much to the commercial team as the relay settings matter to the TSO.

    Busbar differential protection is tested with a scheme-specific commissioning procedure — CT polarity and ratio checks across every circuit into the zone, stability tests against through-fault conditions, and a trip test that has to work correctly across every combination of circuits in and out of service — and a wiring error here is the fault every protection engineer is most careful to rule out.

    Revenue metering CTs and VTs sit on the same busbars but answer to a different authority: the ratio, accuracy class and burden have to be verified and certified for settlement purposes, often by a metering-specific test separate from the protection commissioning programme, and a dispute over that record can cost more than a protection miss.

    Deskely holds busbar zone stability tests, CT ratio verification for both protection and metering, and the metering accuracy certificate in the same bay register, so the commercial metering evidence and the protection commissioning evidence are both traceable to the same CT rather than living in two different contractors' files.

    SF6 HANDLING AND TSO WITNESS POINTSGIS bay compartmentsSF6 GAS COMPARTMENT RECORDSCompartment A1 — busbar6.2 bar, moisture 42 ppmCompartment A2 — CB6.1 bar, moisture 38 ppmCompartment B1 — feeder5.8 bar, leak flaggedTSO WITNESS POINTS — FLAGGED IN ADVANCEPrimary injection, feeder protectionInterlock and permissive verificationBackfeed and first energisation1compartment leak flagged before energisation3witness points named for the TSO's engineerSF6 records sit against the specific compartment, not a general project log.

    How it runs

    From a bay diagram to an energised switch.

    Substation programmes are dominated by sequencing and witness coordination, which is exactly what a structured register makes explicit.

    1. 01

      Parse the design set

      Single line diagrams, protection schematics and cable and point schedules drafted into a reviewed bay register.

    2. 02

      Model interlocks and permissives

      Dependencies between bays and systems recorded so readiness reflects the real switching sequence.

    3. 03

      Template protection and SCADA records

      Injection test, relay setting and point-to-point verification forms defined once per equipment type.

    4. 04

      Run field testing on tablet

      Primary and secondary injection, SF6 handling and control panel checks signed at the bay, offline where needed.

    5. 05

      Flag witness points

      TSO or DNO hold and witness points marked in the register so the right tests are visible to the operator.

    6. 06

      Certify and energise

      Energisation certificates issued from signed records, with carried punch owned and dated.

    FAQ

    Questions about Transmission substations scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.