Strings, inverters, IV curves, grid connection

    Solar farm commissioning software built for tens of thousands of strings and hundreds of inverters, not a handful of assets.

    A utility-scale solar farm turns commissioning into a volume problem: strings, combiner boxes, inverters and transformers repeated hundreds or thousands of times, each needing the same tests recorded the same way. Deskely templates the record set once per equipment type and instantiates it across the whole array, so a hundred-megawatt site is commissioned from structured data rather than a folder of PDFs per inverter.

    Scale
    Thousands of strings
    Test
    IV curve per string
    Gate
    Grid code compliance
    Output
    PAC and energisation
    BLOCK C — INVERTER STATION 14STRING RECORD SET · REV FPV-ARR-14COMBINERINVERTER SKIDMPPT tuningSOLAR FARM BLOCK A — 14 ARRAYS · 1 SKIDTAG REGISTERINV-14Central inverter, station…Records signedINV-14-STR-118String 118, IV curve testIn testMV-14Medium voltage transforme…PreservationFDR-12Collector feeder 12Punch open42 unitsunder one system hierarchy

    The problem

    String testing at scale turns into a spreadsheet nobody trusts by string four thousand.

    IV curve tracing, polarity checks and insulation resistance tests are repeated across every string, combiner box and inverter, and manual data entry from a handheld tracer into a spreadsheet is where transcription errors and missed strings hide.

    Underperforming strings are easy to miss in a flat spreadsheet and expensive to find later, once the array is energised and the fault is buried under production data.

    Deskely holds every string, combiner and inverter as a tagged asset with a templated test record, so an underperforming string is visible against its expected IV curve the day it is tested, not after commercial operation.

    STRING 4,000 IS WHERE THE SPREADSHEET BREAKSIV curve tracing at scaleHandheld tracer readings copied into a flat sheet, string after string144 of thousands of strings shown — underperforming strings are visually identical to good ones on paperWHAT A FLAT SHEET HIDESTranscription error on open-circuit voltage, never recheckedUnderperforming string buried until production data flags it months laterNo baseline IV curve retained for future O&M comparison3underperforming strings found only at commissioning0baseline curves lost when taggedDeskely holds every string's IV curve against its own tag, not a shared spreadsheet row.

    Setting up the register

    Strings, combiners, inverters and trackers are generated from the layout, not typed one by one.

    Single line diagrams and string layout drawings are parsed to generate the full asset register — every string, combiner box, inverter, transformer and tracker — with its position and circuit reference intact.

    One record set is templated per equipment type: string test, combiner box test, inverter commissioning, transformer commissioning, and instantiated automatically across every instance in the array.

    That is what makes a hundred-megawatt site commission on the same structure as a ten-megawatt site, just with more rows.

    1 · SOURCE DOCUMENTSString layout rev F42 stationsInverter register42 unitsDC cabling schedule3 360 stringsIV curve test plan42 stationsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERINV-14Central inverter, station…BLOCK CINV-14-STR-118String 118, IV curve testINV-14MV-14Medium voltage transforme…BLOCK CFDR-12Collector feeder 12COLLECTORTWO DOCUMENTS DISAGREEString layout rev…String 118, IV curve testInverter registerAbbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    String and inverter testing

    IV curve tracing and inverter commissioning are captured on tablet, offline, in the field.

    Technicians work row by row with tablets that stay usable without signal deep in an array, capturing IV curve traces, open-circuit voltage, polarity and insulation resistance against each string tag.

    Inverter commissioning records — communication checks, protection settings, ground fault detection, anti-islanding — are captured per inverter and referenced against the strings feeding it.

    Punch raised during string or inverter testing is categorised for whether it blocks that inverter's commissioning or the wider block's energisation.

    STRING TEST TO ENERGISED BLOCKBlock C · 1,240 stringsIV curve, OCV, insulation resistance — per stringField crew, tablet100%Combiner box test — per combinerField crew100%Inverter commissioning — comms, protection, anti-islandingCommissioning team82%Grid code compliance — ride-through, frequency, ramp rateInterconnection team46%Block energisation certificateOwner's engineer10%1,240strings with a signed IV curve1block energised independent of the othersA block's energisation certificate needs its own strings tested, not a site-wide average.

    Grid connection and compliance

    Grid code compliance testing is the gate between a working plant and a connected one.

    Voltage ride-through, frequency response, reactive power capability and ramp rate tests are recorded against the point of interconnection subsystem, producing the evidence a network operator requires before energisation.

    Deskely gates the energisation certificate on string testing, inverter commissioning and grid compliance testing being complete for the relevant block, so a block cannot be energised while its strings are still untested.

    Because blocks are modelled independently, one section of the array can be energised and generating while another is still under construction.

    Block C — energisation ladderStation records roll up to block energisationDCDC string test completeIssued 02 SepString IV curve tests3 360 / 3 360Polarity and insulationcompleteINVCInverter commissioningBlocked — station 14Inverter parameter set38 / 42 stationsAnti-islanding test34 / 42 stationsACAC energisationBlocked — inverter commissioning openInverter commissioning certnot issuedBlocking punch6 open

    PAC and handover

    Provisional acceptance is issued from string-level evidence, not a sample.

    Provisional acceptance depends on the full string and inverter test set being complete and signed, plus a performance ratio demonstrated during a defined run period — both derived from the same structured data.

    The as-built dossier — every string's IV curve, every inverter's commissioning record, grid compliance results, punch history — is exported to the asset owner and the O&M contractor together.

    That dossier becomes the baseline O&M uses to detect degradation years later, because the original commissioning IV curve for every string is still on file.

    AUDIT QUERYINV-14-STR-118Block C · inverter station 14 · string 118Full history retrieved in one queryINSTMechanical installationEPC contractor04 JunCONTContinuity and polarity checkElectrical technician10 JunIVIV curve testCommissioning engineer22 JunMEGRInsulation resistance testElectrical technician22 JunCERTIFICATEDCDC string test complete02 SepOwner's engineerPrerequisites demonstratedThe AC energisation certificate names the records that permitted it and the punch that was carried.

    Module traceability and DC safety compliance

    A warranty claim years from now starts with a module serial number, and DC arc fault and rapid shutdown compliance has to be proven before the array is ever energised.

    Every module has a serial number, and on a hundred-megawatt site tying that number to its string position, its IV curve result and the installation crew that mounted it is what makes a degradation or warranty claim resolvable years later rather than a site-wide guess.

    DC arc fault detection and rapid shutdown compliance — module-level or string-level shutdown devices responding correctly within the code-mandated time and voltage limits — is tested per combiner or per string before energisation, and it is exactly the kind of test that gets sampled rather than completed in full when a site is racing to interconnect.

    Deskely ties module serial numbers to string position at the point of installation and holds rapid shutdown and arc fault test results against every string tag, so the as-built module map and the DC safety compliance record are both complete rather than reconstructed from installation photos after the fact.

    IV CURVE BASELINE FOR O&MString STR-04812Commissioning IV curve retained as the baseline for future degradation checksSTRING TEST RECORD, RETAINED PER TAGOpen-circuit voltage at commissioningInsulation resistance and polarityCombiner box and circuit referenceYEARS LATER, O&M COMPARES AGAINST THIS1,240baseline IV curves retained across the block1string flagged against its own baseline, not an averageThe original commissioning curve for every string is still on file.

    What the IPP's completion certificate reads

    The plant-level records an owner needs before a utility-scale array is declared ready for commercial operation, not the installer's site sign-off.

    At utility scale the evidence an independent power producer needs is a plant-wide performance case, not a set of individual string checks: inverter block acceptance, collector network integrity and grid compliance all have to close together before the offtake agreement's commercial operation date can be claimed.

    RECORDS PRODUCED6 typesInverter block acceptance test…Commissioning, block by block, ahead of…Medium-voltage collector network…Pre-energisation, before the substation…Grid code compliance and reactive…Pre-synchronisation, witnessed by the…Plant performance ratio…During the performance test period,…SCADA and revenue metering…Before commercial operation is declaredAvailability guarantee test reportAt the guarantee test, ahead of the…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Inverter block acceptance test record

    Each inverter station meets OEM output and protection settings before being connected to the collector network

    Commissioning, block by block, ahead of grid energisation

    Medium-voltage collector network insulation and continuity test

    Underground and overhead collection circuits carry rated current without insulation faults

    Pre-energisation, before the substation is closed in

    Grid code compliance and reactive power test

    The plant's response at the point of interconnection matches the network operator's connection agreement

    Pre-synchronisation, witnessed by the network operator

    Plant performance ratio verification against the energy yield model

    Actual output tracks the bankable yield assumption used in the financing case

    During the performance test period, post-energisation

    SCADA and revenue metering commissioning record

    Plant-level monitoring and settlement metering report data the offtake agreement can be billed against

    Before commercial operation is declared

    Availability guarantee test report

    The plant meets its contracted availability threshold across the test window

    At the guarantee test, ahead of the commercial operation date

    How it runs

    From layout drawing to an energised, compliant array.

    Utility-scale solar rewards generating the register from drawings rather than typing it, because the volume of repeated assets is the whole challenge.

    1. 01

      Parse the layout

      Single line diagrams and string layouts turned into a full register of strings, combiners, inverters and transformers.

    2. 02

      Template per equipment type

      String, combiner, inverter and transformer record sets defined once and instantiated across every instance.

    3. 03

      Capture IV curve tracing offline

      String tests recorded on tablet in the field, working without signal deep in the array.

    4. 04

      Commission inverters and blocks

      Protection, communication and anti-islanding settings recorded per inverter, referenced to their strings.

    5. 05

      Run grid compliance tests

      Voltage ride-through, frequency response and reactive power tests recorded against the interconnection.

    6. 06

      Energise block by block

      Energisation and PAC certificates issued per block from signed string, inverter and grid compliance records.

    FAQ

    Questions about Utility-scale solar scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.