Dewatering, wet commissioning, runaway test

    Hydropower commissioning software built for wet commissioning, runaway speed tests and civil works that never quite finish on schedule.

    A hydro unit is proven in stages that civil, mechanical and electrical scope have to hand off cleanly: dewatered inspection, dry commissioning, wet commissioning under head, and a runaway speed test that only happens once per unit if it goes well. Deskely tracks each unit and its balance of plant as tagged subsystems, so a powerhouse with four units at four different stages stays legible.

    Unit
    Turbine, generator, governor
    Stages
    Dry, wet, load, runaway
    Constraint
    Head and flow availability
    Gate
    Unit energisation
    POWERHOUSE — UNIT 2UNIT RECORD SET · REV CPENSTOCKTURBINEGENERATORHP-GEN-01TAILRACERESERVOIRheadrace gateTAG REGISTERU2-TRB-01Turbine runner, unit 2Records signedU2-WKG-04Wicket gate ring, unit 2In testU2-GEN-01Generator statorPreservationPMP-03Governor oil pressure uni…Punch open1 set / unitunder one system hierarchy

    The problem

    Four units, four stages, and a spreadsheet that cannot show any of it at once.

    One unit may still be dewatered for penstock inspection while another is under load testing and a third is waiting on a runaway speed test slot that depends on reservoir level.

    Civil defects found during dewatering, mechanical punch from the dry run and electrical findings from wet commissioning all land against the same unit, but rarely in the same document.

    Deskely holds each unit's mechanical, electrical, governor and protection records against one tag set, so the status of unit three is a filter, not a phone call to the site.

    FOUR UNITS, FOUR STAGESPowerhouse — one spreadsheetA single project tracker cannot show all four states at onceUnit 1Energised, on loadUnit 2Wet commissioning under headUnit 3Runaway test slot pending reservoir levelUnit 4Dewatered for penstock inspectionWHAT LEAKS BETWEEN STAGESCivil defect found dewatering unit 4, not visible at unit 3's runaway gateWet commissioning results on unit 2 sit in a different document to dry checksDeskely holds each unit's stages on one tag, so a status is a filter, not a phone call.

    Setting up the register

    Penstock, turbine, generator and governor are subsystems within each unit tag.

    The powerhouse is modelled by unit, with penstock and intake, turbine and wicket gates, generator and excitation, governor and hydraulic system, and protection each held as subsystems under that unit.

    Single line diagrams, hydraulic schematics and equipment lists are parsed into a reviewed register, so mechanical and electrical scope share the same tag rather than parallel spreadsheets.

    Balance of plant — intake gates, spillway, switchyard, auxiliary power — is modelled the same way, so a unit's readiness reflects what it actually depends on.

    1 · SOURCE DOCUMENTSUnit general arrangement…3 unitsTurbine and governor pac…1 set / unitPenstock isometrics6 linesGenerator and excitation…3 setsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERU2-TRB-01Turbine runner, unit 2UNIT 2U2-WKG-04Wicket gate ring, unit 2UNIT 2U2-GEN-01Generator statorUNIT 2PMP-03Governor oil pressure uni…GOVERNORTWO DOCUMENTS DISAGREEUnit general arra…Wicket gate ring, unit 2Turbine and gover…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Dewatering and wet commissioning

    Dewatered inspection and wet commissioning are separate record sets, not one long checklist.

    Dewatered inspections of the penstock, spiral case, draft tube and wicket gates are captured with photos and findings before the unit is ever put under head, and each finding is categorised for whether it blocks re-watering.

    Wet commissioning — bearing temperatures, vibration, seal leakage, governor response under flow — is recorded stage by stage as head is applied, with the record set held against the same unit tag.

    Because dewatered findings and wet commissioning results sit on one tag, a civil defect found before re-watering is still visible when the unit reaches load testing.

    DEWATERED TO ENERGISED, PER UNITUnit 3 gate ladderDewatered inspection — penstock, draft tubeSigned offDry commissioning — mechanical checksSigned offWet commissioning under headSigned offOverspeed protection and governor sign-offIn progressRunaway speed testAwaiting predecessorUnit energisation certificateAwaiting predecessor3of 6 gates cleared, unit 34units, each on its own ladderThe runaway test is authorised only once overspeed protection is signed, not assumed.

    Runaway speed test

    The runaway test is high-consequence and the prerequisites are checked, not assumed.

    A turbine runaway speed test is run deliberately once per unit, and every prerequisite — governor settings, overspeed protection, vibration monitoring, bearing condition — needs to be signed off before the test is authorised.

    Deskely gates the runaway test record on those prerequisites, so the test cannot be logged as authorised while overspeed protection or governor commissioning is still open.

    Results — peak speed, duration, bearing and vibration behaviour during the event — are captured against the unit and referenced by the unit energisation certificate that follows.

    Unit 2 — wet commissioning ladderEach certificate issues only from signed records beneath itDRYDry commissioningIssued 11 MayGovernor loop checkscompleteRunner alignment recordin toleranceWETWet commissioningReady — reservoir level confirmedPenstock filling recordcompleteWicket gate seal testpassedLALoad acceptanceBlocked — 3 itemsBlocking punch3 openRunaway speed testnot started

    Handover per unit

    Each unit is energised and handed over on its own timeline, independent of the others.

    Because units are modelled independently, unit one can be energised and generating while unit four is still dewatered for civil remediation, without either status confusing the other.

    The operations team receives a per-unit dossier — dewatering findings, wet commissioning results, runaway test evidence, protection settings and punch history — as each unit closes out.

    Preservation routines cover units and auxiliary equipment awaiting energisation, so long idle periods between civil completion and electrical readiness do not become a source of new defects.

    AUDIT QUERYU2-WKG-04Powerhouse · unit 2 · wicket gateFull history retrieved in one queryINSTMechanical installationTurbine vendor20 JanALGNGate ring alignmentTurbine vendor02 FebSEALSeal pressure testCommissioning engineer18 FebWETWet commissioning recordCommissioning engineer09 MayCERTIFICATEWETWet commissioning11 MayOwner's engineerPrerequisites demonstratedThe load acceptance certificate names the records that permitted it and the punch that was carried.

    Environmental flow, spillway gates and fish passage

    A hydro scheme is licensed on more than megawatts, and compensation flow, spillway gate operability and fish passage systems have to be proven before the environmental regulator signs off.

    Alongside the powerhouse, a hydro licence typically obliges the operator to release a minimum compensation or environmental flow, operate spillway and intake gates through their full range under load, and keep fish passage or screening systems functional — none of which is generation equipment, but all of which can hold up commercial operation as tightly as a turbine fault.

    These systems are commissioned by a different discipline again — civil and hydraulic, not electrical — on a schedule that depends on river conditions and consent windows rather than the powerhouse programme, and their test evidence tends to end up in a separate environmental compliance file that nobody cross-checks against unit readiness.

    Deskely holds spillway gate operability tests, compensation flow monitoring records and fish passage functional checks as subsystems in the same register as the units, so the environmental regulator's evidence pack and the unit energisation dossier are built from the same signed records rather than reconciled by hand.

    PER-UNIT ENERGISATION DOSSIERIndependent unit timelinesUnit 1EnergisedUnit 2Wet commissioningUnit 3Runaway test pendingUnit 4Dewatered, civil remediationWHAT EACH UNIT'S DOSSIER HOLDSDewatering findings and photosWet commissioning results by stageRunaway test evidence and protection settings4independent unit dossiers, one powerhousePreservation runs on units awaiting energisation without confusing another unit's status.

    What the dam safety and grid panel reads

    The mechanical and civil records a hydro scheme needs before water is put through a unit under load.

    A hydro unit sits behind civil works that are commissioned once for the life of the scheme and mechanical plant that is tested unit by unit. The dossier keeps spiral case pressure tests, governor tuning and unit spin records against the same tag the dam safety authority and the grid operator both review.

    RECORDS PRODUCED6 typesHydro unit spin and overspeed test…During unit commissioning, before grid…Spiral case and penstock…Pre-commissioning, before first water…Governor and load rejection test…Commissioning, before the unit is…Intake gate and trash rack…Before first water is admitted to the…Spillway and outlet works capacity…Before the reservoir is filled to normal…Unit efficiency and capacity test…During the performance test, after grid…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Hydro unit spin and overspeed test record

    The runner, shaft and governor hold stable speed and trip correctly at the overspeed setting

    During unit commissioning, before grid synchronisation

    Spiral case and penstock hydrostatic test certificate

    The pressure boundary carries head without leakage or deformation

    Pre-commissioning, before first water admission

    Governor and load rejection test record

    The unit responds to load changes and full rejection without exceeding pressure or speed limits

    Commissioning, before the unit is released for grid duty

    Intake gate and trash rack functional test

    Water intake control operates correctly across its full range under head

    Before first water is admitted to the unit

    Spillway and outlet works capacity verification

    Flood discharge capacity meets the design flow at the reservoir's operating levels

    Before the reservoir is filled to normal operating level

    Unit efficiency and capacity test report

    Output across the operating head range meets the contractual guarantee

    During the performance test, after grid synchronisation

    How it runs

    From dewatered inspection to unit energisation.

    Hydro projects reward a unit-based structure from the outset, because civil, mechanical and electrical scope hand off to each other repeatedly per unit rather than once for the plant.

    1. 01

      Model by unit

      Penstock, turbine, generator, governor and protection held as subsystems under each unit tag.

    2. 02

      Parse the tag register

      Single lines, hydraulic schematics and equipment lists drafted into a reviewed register per unit.

    3. 03

      Capture dewatered inspections

      Penstock, spiral case, draft tube and wicket gate findings recorded with photos before re-watering.

    4. 04

      Record wet commissioning

      Bearing, vibration, seal and governor results captured stage by stage as head is applied.

    5. 05

      Gate the runaway test

      Overspeed protection and governor prerequisites signed before the runaway speed test is authorised.

    6. 06

      Energise and hand over per unit

      Unit energisation certificate issued from signed records, dossier exported unit by unit.

    FAQ

    Questions about Hydropower scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.