Solar and energy storage

    Commissioning software for solar and storage assets that have to reach COD with every string, rack and inverter proven.

    Solar and energy storage projects share a common rhythm: install thousands of repetitive assets, test them in sequence, prove grid code compliance and hand over a complete dossier before commercial operation. Deskely holds the tag register, string tests, inverter records, BESS container checks and protection settings in one system, so energisation and COD readiness are visible block by block.

    The problem

    Repetitive scale, with a single energisation gate.

    A solar farm or BESS plant is not a few large systems — it is thousands of strings, hundreds of combiner boxes, dozens of inverters or containers, and one substation that cannot energise until the evidence beneath it is complete. Spreadsheets hide which block is actually ready.

    String and rack records scatter

    IV curve tests, insulation resistance and torque records are captured in subcontractor files, so block readiness has to be reconstructed before every energisation review.

    Inverter and BESS commissioning runs in parallel silos

    PV inverters, battery containers and power conversion systems each have their own commissioning reports, disconnected from the shared point of interconnection.

    Grid code compliance is proven late

    Protection settings, anti-islanding tests and reactive-power capability are gathered after energisation, delaying the PAC and COD milestones.

    Preservation records get lost before energisation

    Modules, inverters and BESS containers sit through weather, dust and humidity between delivery and energisation, and their preservation evidence is rarely tied to the asset.

    How it runs

    From module delivery to commercial operation.

    1. 01

      Register and parse

      Equipment lists, string layouts and single line diagrams become a reviewed tag register with block, row and inverter hierarchy.

    2. 02

      String and block testing

      IV curves, insulation, torque and functional checks are signed per string and combiner, gating each inverter block.

    3. 03

      Inverter, tracker and BESS commissioning

      Inverter start-up, tracker calibration, battery management and power conversion checks are completed against each asset.

    4. 04

      Substation energisation and COD

      Protection settings, grid code tests and reliability runs are held against the substation and POI, then exported for PAC and COD.

    RAMP-UP READINESS BY INVERTER BLOCKPre-commissioningPanels, racking and wiring checked01100%String and inverter testingIV curves and inverter start-up02100%Energisation and grid codeProtection settings and utility witness0354%Reliability run and PACPerformance ratio proving underway0418%Every inverter block and battery container reports from the same records — no separate vendor spreadsheet.

    Side by side

    Spreadsheets versus a single energisation record.

    At the pre-COD review the question is always the same: which block is actually ready to energise today, and what evidence proves it?

    Spreadsheets versus a single energisation record.
    AspectSubcontractor files and spreadsheetsDeskely
    String readinessReconstructed from IV curve spreadsheets before each review.Live per string, rolled up to combiner, inverter and block.
    Inverter and BESS recordsHeld in separate commissioning reports per vendor.Signed against the asset in the same register as the strings.
    Grid code evidenceGathered after energisation for PAC submission.Captured during start-up and tied to the POI from day one.
    Tracker acceptanceChecked row by row on paper with no central view.Zone-by-zone tracker calibration and logic tests visible in one place.
    Preservation historyLost or stored separately from the asset.Tied to the tag from delivery through energisation.
    COD dossierAssembled from scattered files after the fact.Exported as a structured evidence package on demand.

    What changes

    Per string

    readiness across the whole array

    Block-by-block

    energisation gating before COD

    Live

    grid code and protection evidence

    Day one

    COD dossier for owner and lender

    Before you shortlist

    Estimate what your current process costs

    Enter your tag count and record handling time to see the admin hours and cost in play — then book a demo against your own numbers.

    Open the ROI calculator

    FAQ

    Questions about solar and energy storage.

    Project types

    The same completions ladder, from a string test to a battery dispatch.

    What changes between solar and storage scopes is the equipment breakdown, which vendor rep witnesses the test and what the utility wants to see before energisation. The record types, the gates and the audit trail behind them do not.

    01

    Utility-scale solar farm commissioning

    A utility-scale solar farm is a repetitive build at enormous scale: module strings wired into combiner boxes, feeding central or string inverters, stepped up through an on-site substation to the grid. Deskely holds every string, inverter, tracker row and transformer in one register with the mechanical completion, energisation and commercial operation date (COD) gates built in.

    See this scope in detail
    02

    Commercial rooftop solar commissioning

    A commercial rooftop programme is rarely one building: it is a portfolio of warehouse, retail and office roofs, each with its own array layout, inverter set, structural load assessment and utility net metering application. Deskely holds every site, array and inverter in one register, so a portfolio manager can see which buildings are ready for permission-to-operate without chasing a separate file per roof.

    See this scope in detail
    03

    Battery energy storage system (BESS) commissioning

    A battery energy storage system commissions life-safety systems a solar array never touches: battery modules and racks, power conversion system (PCS) units, thermal management, gas detection and fire suppression, all sitting inside containers or buildings that have to be proven safe before any energy is stored. Deskely holds every rack, PCS unit and safety system in one register with the statutory fire and electrical sign-off gates built in.

    See this scope in detail
    04

    Solar-plus-storage hybrid commissioning

    A hybrid plant pairs a PV array with a co-located BESS behind a single point of interconnection, with a hybrid inverter or shared PCS coordinating charge, discharge and export. Deskely holds the solar side and the storage side in one register with a shared interconnection gate, so the plant's dispatch and grid-support functions are proven together rather than each half assuming the other is ready.

    See this scope in detail
    05

    Floating solar (floatovoltaics) commissioning

    A floating solar installation adds a marine dimension a ground-mount array never faces: pontoon float assembly, mooring and anchoring systems rated for water level fluctuation and wind loading, and submarine or floating cable runs to the shoreline substation. Deskely holds every pontoon block, mooring point and cable run in one register with the marine structural and electrical sign-off gates built in.

    See this scope in detail
    06

    Solar tracker system commissioning

    A single-axis tracker system is a control problem layered on top of a mechanical one: every row has a slew drive, a controller and a comms link back to a master, and the row's backtracking and stow logic has to be correct before the row is allowed anywhere near production. Deskely holds every tracker row, controller and comms segment in one register with the calibration and control network acceptance gates built in.

    See this scope in detail
    07

    Solar substation and grid connection commissioning

    A solar plant's collector substation steps generation up from the plant's medium-voltage collection system to transmission voltage, and it is commissioned to the same rigour as any grid-connected substation: switchgear, power transformers, protection relays and SCADA all individually tested and coordinated before the utility will allow the plant to close in. Deskely holds every bay, transformer and relay in one register with the protection testing and energisation gates built in.

    See this scope in detail
    08

    Green hydrogen electrolyser commissioning

    A green hydrogen plant pairs electrolyser stacks fed by renewable power with purification, compression and storage systems handling a gas that is unforgiving of shortcuts. Deskely holds every stack, skid and safety device in one register with the hydrogen-specific safety gates — leak testing, purge verification, gas detection — built in ahead of the electrical and process commissioning gates.

    See this scope in detail
    09

    Carbon capture and storage (CCS) commissioning

    A CCS project spans three distinct scopes that are rarely run by the same contractor: a capture train stripping CO2 from flue gas, a compression and pipeline system moving it to a storage site, and injection wells putting it underground under a monitoring, reporting and verification (MRV) plan regulators will audit for decades. Deskely holds all three scopes in one register with the pressure testing, compression commissioning and injection well gates built in.

    See this scope in detail
    10

    Biogas and biomass plant commissioning

    A biogas or biomass plant runs three distinct processes in sequence: anaerobic digestion or fuel handling and combustion, gas upgrading or flue gas treatment, and power generation or gas injection to the grid. Deskely holds every digester, skid and combustion asset in one register with the process safety, gas quality and export gates built in.

    See this scope in detail

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.