Capture trains, compression and injection wells proven ahead of first CO2

    Commissioning software for carbon capture and storage where capture trains, compression trains and injection wells each carry their own test regime that has to close out before the first tonne of CO2 moves.

    A CCS project spans three distinct scopes that are rarely run by the same contractor: a capture train stripping CO2 from flue gas, a compression and pipeline system moving it to a storage site, and injection wells putting it underground under a monitoring, reporting and verification (MRV) plan regulators will audit for decades. Deskely holds all three scopes in one register with the pressure testing, compression commissioning and injection well gates built in.

    Assets
    Capture columns, compressors, pipeline, injection wells
    Test
    Capture train test, pipeline hydrotest, well integrity test
    Compliance
    Monitoring, reporting and verification (MRV) plan
    Gate
    Fit for first CO2 injection
    CCS TRAIN — ABSORBER ACCS COMMISSIONING RECORD SET · REV DABSORBER — CAPTURE TRAIN 2COMPRESSOR COMP-CO2-02PIPELINE SECTION 14INJECTION WELL 03CAP-T2-01Monitoring string pendingTAG REGISTERABS-AAbsorber vessel, train ARecords signedCOMP-A1CO2 compressor, train AIn testWELL-05Injection well 05PreservationPIPE-ACO2 pipeline, train APunch open36 reportsunder one system hierarchy

    The problem

    Capture, compression and injection are three different projects run by three different contractors, and a regulator will ask for one continuous evidence trail across all of them.

    The capture train, the compression and pipeline system, and the injection wells are typically engineered, procured and commissioned by separate contractors on separate schedules, each with its own test regime and its own definition of mechanical completion.

    When capture train test data, pipeline hydrotest records and injection well integrity tests sit in three separate contractor closeout packages, nobody can assemble the single evidence trail an MRV plan and its regulator will expect before CO2 is allowed underground.

    Deskely holds capture, compression and injection assets in one register with a shared readiness model, so first-injection readiness reflects evidence across the whole chain rather than three contractors each declaring their own scope complete.

    THREE CLOSEOUT BINDERS, ONE MRV PLANCapture → compression → injectionCapture trainContractor Acloseout completeCompression + pipelineContractor Bcommissioning nowInjection wellsContractor Cnot startedEach contractor defines mechanical completion its own wayWHAT THE REGULATOR WILL AUDITCapture train performance dataPipeline hydrotest certificates, per sectionWell casing pressure test and MIT resultsOne continuous evidence trail, capture to well3contractors, each with a different definition of done0tonnes of CO2 injected until the chain is provenDeskely holds capture, compression and injection in one register with a shared readiness model.

    Setting up the register

    Capture columns, compressors, pipeline and wells are tagged assets spanning three commissioning scopes.

    P&IDs for the capture train, pipeline route drawings and injection well schematics are parsed into a reviewed register, so every absorber column, compressor, pipeline section and well carries its design data and test requirement from day one.

    Capture train commissioning templates, CO2 compressor acceptance tests and pipeline hydrotest procedures are templated once per equipment type, respecting the different contractors and standards each scope is built to.

    Injection well integrity testing — casing pressure tests, cement bond logs and mechanical integrity tests — is held as its own record set tied to the MRV plan's monitoring requirements, distinct from surface facility commissioning.

    1 · SOURCE DOCUMENTSCapture train P&IDs32 sheetsAbsorber test reports36 reportsCompressor performance t…12 recordsInjection well logs24 logsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERABS-AAbsorber vessel, train AABSORBERCOMP-A1CO2 compressor, train ACOMPWELL-05Injection well 05WELLPIPE-ACO2 pipeline, train APIPETWO DOCUMENTS DISAGREECapture train P&I…Injection well 05Absorber test rep…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Execution

    Capture, compression and well testing are gated independently, then rolled up into one first-injection readiness view.

    Capture train commissioning proves absorber and stripper performance against design CO2 capture rate, while compressor trains are tested through their full pressure ratio range with vibration and surge protection verified before pipeline tie-in.

    Pipeline sections undergo hydrotesting and integrity verification against the design code, with records captured per section so a hydrotest failure on one segment does not obscure the readiness of the rest of the route.

    Injection wells are proven through mechanical integrity testing and casing pressure tests, with findings logged against the specific well, so first-injection readiness is reported well by well rather than assumed once drilling is reported complete.

    FIRST INJECTION LADDERCapture → compression → wellCapture train performance testSigned offCompressor acceptance and pipeline hydrotestIn progressInjection well mechanical integrity testAwaiting predecessorMRV plan evidence chain assembledAwaiting predecessorFirst CO2 injection authorisedAwaiting predecessor1 of 5gates cleared across the full chain3contractor scopes rolled into one readiness viewFirst injection is authorised from evidence spanning all three scopes, not one.

    First injection and handover to operations

    First injection is authorised from a chain of signed evidence, spanning capture, compression and the well, because that is what the MRV plan and the regulator will expect to audit.

    Capture train performance data, compressor commissioning reports, pipeline hydrotest certificates and well integrity test results all export from the same register, so the first-injection evidence package satisfies the MRV plan in one submission.

    The handover pack for the operations and monitoring team includes as-built process data, pipeline integrity baselines and well test data keyed to the register, giving the long-term monitoring programme the same starting evidence used to authorise injection.

    Every signature carries a name, role and timestamp, which is what the regulator, the storage site operator and the asset owner's insurer will ask for before CO2 injection is authorised rather than trialled.

    AUDIT QUERYWELL-05Injection well 05Complete evidence chain for WELL-05WELL-PERMInjection well permitRegulatorpendingPIPE-PRESPipeline pressure testPipeline operatorpendingABS-TESTAbsorber pressure testCapture OEM15 MarCERTIFICATEFC-TCFirst capture — train CpendingRegulatorPrerequisites demonstratedFirst capture is blocked until the injection well permit and pipeline pressure test are signed.

    The dossier

    First injection is a baseline, not an endpoint, for a monitoring programme regulators expect for decades.

    The monitoring, reporting and verification plan's instruments have to be calibrated and baselined before first injection, because every later reading is judged against that baseline. The dossier keeps capture-side purity evidence and well integrity records tied to their own tags and schedules.

    RECORDS PRODUCED6 typesCO2 purity certificateon each batch prior to transport or…Capture unit commissioning reportat first sustained operation of the…Injection well integrity test…before first injection into the wellMRV instrument calibration and…before first injection, referenced for…Mechanical integrity re-test…on the periodic interval set by the…Injection rate and pressure…continuously through injection…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    CO2 purity certificate

    captured CO2 meets the pipeline or injection specification for moisture and contaminant content

    on each batch prior to transport or injection

    Capture unit commissioning report

    the amine or equivalent capture process removes CO2 at the design capture rate

    at first sustained operation of the capture unit

    Injection well integrity test record

    casing and wellhead integrity meet the design pressure rating before injection begins

    before first injection into the well

    MRV instrument calibration and baseline record

    downhole pressure, seismic and groundwater monitoring instruments are calibrated with a recorded baseline reading

    before first injection, referenced for the life of the MRV plan

    Mechanical integrity re-test record

    the injection well continues to meet its integrity criteria on the schedule the MRV plan requires

    on the periodic interval set by the regulator

    Injection rate and pressure compliance record

    actual injection operations stayed within the permitted rate and pressure envelope

    continuously through injection operations, reported to the regulator

    How it runs

    From three contractor scopes to one first-injection readiness view.

    CCS programmes reward a register that spans capture, compression and injection from the outset, because the MRV plan will ask for a continuous evidence trail across all three, not three separate closeout binders.

    1. 01

      Model the full chain

      Capture columns, compressors, pipeline sections and injection wells modelled as assets across all three commissioning scopes.

    2. 02

      Parse P&IDs and well schematics

      Capture train P&IDs, pipeline drawings and injection well schematics drafted into one reviewed register with design data attached.

    3. 03

      Template each scope's tests

      Capture train, compressor acceptance, pipeline hydrotest and well integrity tests defined once per equipment type, instantiated across every asset.

    4. 04

      Gate first injection on the full chain

      First-injection readiness reported only once capture, compression and well records are all signed, satisfying the MRV plan in one export.

    FAQ

    Questions about Carbon capture and storage scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.