FPSO Demo Project › Topsides › Utilities › All systems
Mechanical completion41
582-82-01Service water lift pumps92%ITRs 166/180Punch A 1
582-83-02Fire water ring main74%ITRs 133/180Punch A 4
586-11-01HV switchboard61%ITRs 110/180Punch A 7
Pre-commissioning29
582-82-02Service water distribution88%ITRs 158/180Punch A 2
430-01-01Seawater lift57%ITRs 103/180Punch A 7
Commissioning18
210-02-01Gas export71%ITRs 128/180Punch A 5
300-01-03HP separation45%ITRs 81/180Punch A 9
Handed over24
582-95-02Instrument air header100%ITRs 180/180Punch A 0
860-03-04Deck lighting100%ITRs 180/180Punch A 0
Overview
Core is the completions system of record: the live tag register with every inspection, punch item, preservation task, procedure and certificate attached to the tag it belongs to, from the yard to the field. It has run FPSO completions since 2014.
Core is part of Deskely Build, one of four suites across the life of a project. Every product reads from and writes to the same tag register, so each stage starts with clean data from the last.
Used by completions managers, commissioning leads, discipline engineers, owner's representatives and contractors.
What Core replaces.
Completions tracked in spreadsheets and email.
Inbox2 unread
Lead, MechanicalRE: RE: ITR status 582-82-0109:12
Site QCFW: Punch list deck B (photos)08:47
CompletionsTracker v14 attachedMon
Client repRE: MC certificate 582-82-01?Mon
Lead, InstrumentRE: RE: RE: ITR status 582-82-01Fri
ContractorUpdated punch list v6Fri
Completions_tracker_v14_FINAL.xlsx
ABCDE
1SubsystemA-ITRB-ITRPunch AStatus
2582-82-0146/4812/203In progress
3582-82-0231/318/14?In progress
4582-21-0322/400/127Behind
5582-21-0418/26
6
7
8
9
10
11
TodayA tracker per discipline, rebuilt from emails, and never quite the same twice.