Checksheets/TestpackTP-82-007 Service water discharge
✦ Built from line list and drawings
BuiltWalked downTestedReinstatedClosed
LineSizeDesignTestMedium
582-SW-820001-8"8 in16 barg24 bargWater
582-SW-820002-8"8 in16 barg24 bargWater
582-SW-820021-4"4 in16 barg24 bargWater
582-SW-820044-2"2 in16 barg24 bargWater
Reinstatement
✓Spades removed
✓Instruments reinstalled
✓Gaskets replaced
Vents and drains closed
Line walked after reinstatement
Overview
Testpack builds pressure test packs from the line list and the drawings, records the test in the field, and tracks every spade, gasket and instrument back in before the pack is closed.
Testpack is part of Deskely Build, one of four suites across the life of a project. Every product reads from and writes to the same tag register, so each stage starts with clean data from the last.
Used by piping and mechanical engineers, test supervisors, qa/qc engineers and commissioning leads.
What Testpack replaces.
Test packs built by hand from the line list.
Line list_582-82_rev4.xlsx
ABCD
1Line NoDesign PTest PMedium
26"-SW-82001-A116 barg24 bargWater
34"-SW-82002-A116 barg24 bargWater
42"-SW-82014-A116 barg42 bargWater
53"-FW-63001-B212 barg18 bargWater
6
7
8
9
10
11
TP-582-82-014_reinstatement.pdf1 / 1
REINSTATEMENTPACK 014
Spade S-01out ✓
Spade S-02–not ticked
Gasket G-03new ✓
PT-820045back in?
Vent V-07shut ✓
TodayLines copied from the line list into a pack, and reinstatement ticked off on paper.
TP-582-82-014 · Seawater lift linesTest pack
LineDesign PTest PMedium
6"-SW-82001-A116 barg24 bargWater
4"-SW-82002-A116 barg24 bargWater
2"-SW-82014-A116 barg24 bargWater
2"-SW-82015-A116 barg24 bargWater
Reinstatement 14 of 16 back in · the pack stays open
With TestpackPacks built with lines, limits and medium filled in, and every item tracked back in.
How Testpack works
From line list to closed pack.
What happens to a test pack, from the line list to reinstatement.
01Build the pack
Lines in the test boundary come from the line list and the drawings, with design pressure, test pressure and medium filled in.
Commissioning & InspectionSearch...EnglishRS
Test packs›TP-582-82-014
TP-582-82-014 · Seawater lift lines✦ AIBuilt
Hydrostatic test · Boundary on 582-82-PR-PID-00001 · Lines from line list rev 4
Release for walkdown
Built2Walked down3Tested4Reinstated5Closed
LineSizeDesign PTest PMediumIsometrics
6"-SW-82001-A16"16 barg24 bargWater6 sheets
4"-SW-82002-A14"16 barg24 bargWater5 sheets
2"-SW-82014-A12"16 barg24 bargWater4 sheets
2"-SW-82015-A12"16 barg24 bargWater3 sheets
4 lines in the boundaryFrom line list rev 4
Built from the line list
4 lines, 18 isometric sheets and 16 items to reinstate, with design pressure, test pressure and medium filled in.
Test limits
Test pressure
24 barg
Medium
Water
Gauge range
0 to 40 barg
Witness
Client
02Test in the field
The test is recorded with readings, photos and signatures, and witnesses sign in the field app.
Commissioning & InspectionSearch...EnglishRS
Test packs›TP-582-82-014
TP-582-82-014 · Seawater lift lines✦ AITesting
Hydrostatic test · Boundary on 582-82-PR-PID-00001 · Lines from line list rev 4
BuiltWalked down3Tested4Reinstated5Closed
Pressure recordHeld at 24.0 barg
TimePressureTemp.
10:2024.1 barg14 °C
11:2024.0 barg14 °C
12:2024.0 barg15 °C
Witnesses2 of 2 signed
Test supervisorSigned in the field app · 12:24J.M.
Client witnessSigned in the field app · 12:26K.L.
Attachments
Gauge certificate
PG-114 · valid to Mar 2027
Photos
3
03Reinstate every item
Every spade, gasket, instrument, vent and drain is listed and ticked back in.