Certificates/Dossier582-82-01 Service water lift pumps
✦ 516 of 537 documents · 3 gaps
Dossier indexClient structure v2
✓1Certificates4/4
✓2A-ITRs214/214
!3B-ITRs196/214
✓4Punch list and closures38/38
✓5Test packs3/3
✓6Commissioning procedures4/4
!7Vendor documents46/48
!8As-built drawings11/12
Before the client sees it
Missing18 B-ITRs not yet signedInstrument · due 24 Oct
Out of datePump manual on Rev 1, Rev 3 issuedVendor docs · PumpTech
Out of dateAs-built PID-003 in draftingFrom Redline · AB2, AB3
12345678
Send gaps to ownersPreview PDF
Overview
Dossier assembles each subsystem's handover dossier in the client's own structure, from the records already in Deskely, checks every page and flags what is missing before the client sees it.
Dossier is part of Deskely Operate, one of four suites across the life of a project. Every product reads from and writes to the same tag register, so each stage starts with clean data from the last.
Used by completions and handover teams, document control, client handover reviewers and operator readiness teams.
What Dossier replaces.
Assembling dossiers page by page.
Dossier_582-82-01/7 items
PDF01 MC certificate.pdf2 pages
PDF02 A-ITRs_scanned.pdf312 pages
PDF03 B-ITRs_scanned.pdf188 pages
XLSX04 Punch list_v6.xlsx1 sheet
PDF05 Test packs.pdf96 pages
06 Vendor documents/41 files
07 As-builts/Empty
Dossier_582-82-01_final.pdf1 / 824
unsigned?
TodayPages pulled from every system, scanned into one PDF, and checked by flicking through.
Dossier · 582-82-01 Seawater LiftChecked
SectionDocumentsStatus
1 Certificates4 / 4Complete
2 A-ITRs46 / 482 missing
3 B-ITRs20 / 20Complete
4 Punch1 cat. A openHeld
5 Test packs6 / 6Complete
6 Vendor documents40 / 41Old revision
Gap list sent to owners with due dates
With DossierEach subsystem's dossier in the client's structure, every page checked, gaps flagged with owners.
How Dossier works
From records to accepted dossier.
What happens to a subsystem's handover dossier.
01Set up the structure once
The client's index, sections and rules for each section are used for every subsystem.
Commissioning & InspectionSearch...EnglishRS
Dossiers›Structure
Dossier structure · DOS-STD-04
The client's index, set up once and used for every subsystem.