BMS, HVAC and TAB against a fixed CAT A date

    Commissioning software for office buildings where the BMS, HVAC and life safety systems all have to prove out before practical completion.

    A commercial office building lives or dies on its M&E: chillers, AHUs, VAV boxes, BMS points and fire alarm cause-and-effect all have to be pre-functionally checked, functionally tested and balanced before the building is handed to a tenant fit-out team. Deskely holds every system, asset and test in one register with the Cx process and PC gate built in.

    Systems
    HVAC, BMS, electrical, fire
    Process
    PFC, FPT, IST, TAB
    Gate
    Practical completion
    Credits
    LEED / BREEAM Cx
    TOWER B — FLOORS 12-18BUILDING SERVICES RECORD SET · REV CTOWER A — FLOORS 1–16RISERL07-AHU-02FLOOR 7 FIT-OUTTAG REGISTERAHU-04Floor 12-14 air handling …Records signedFCU-12-03Fan coil unit, tenant zon…In testBMS-CTRL-07BMS controller, floor 14PreservationSMK-EX-01Smoke extract fan, core BPunch open5 180 pointsunder one system hierarchy

    The problem

    Every M&E subcontractor commissions its own system and calls it done.

    The mechanical contractor balances the air. The controls contractor points-checks the BMS. The fire alarm installer signs its own cause-and-effect matrix. None of it is tested together until the CxA turns up asking for an integrated systems test that nobody planned time for.

    When status lives in separate O&M binders and disconnected spreadsheets, the developer cannot answer a simple question: is this floor actually ready for CAT A handover.

    Deskely puts every asset and every test in one register with one status model, so PC readiness is derived from signed records instead of assembled the week before handover.

    EACH SUBCONTRACTOR SIGNS ITS OWN SYSTEMCAT A floor, three tradesMechanical, controls and fire each declare completion independentlyMechanical — TAB reportBalanced, contractor signedControls — BMS point-to-pointPoints checked, contractor signedFire — cause and effect matrixVendor witness onlyNOBODY HAS TESTED THEM TOGETHERThe CxA asks for an integrated systems test the week before handover3 of 3systems declared complete, none tested as onePCcannot be derived from three separate bindersDeskely holds every system's tests in one register, so PC readiness is derived, not assembled.

    Setting up the register

    AHUs, chillers, VAV boxes and BMS points are tagged assets with their own test set.

    Mechanical schedules, electrical single lines, BMS point lists and fire alarm cause-and-effect matrices are parsed into a reviewed register, so every damper, valve and point carries its drawing reference from day one.

    Pre-functional checklists, functional performance tests and TAB reports are templated once per asset type and instantiated across every floor.

    That structure is what allows one floor to reach PC while the shell and core team is still working two floors above.

    1 · SOURCE DOCUMENTSM&E drawings rev C84 sheetsBMS point schedule5 180 pointsFCU schedule312 unitsFire strategy drawings22 floorsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERAHU-04Floor 12-14 air handling …LEVEL 12FCU-12-03Fan coil unit, tenant zon…LEVEL 12BMS-CTRL-07BMS controller, floor 14CONTROLSSMK-EX-01Smoke extract fan, core BLIFE SAFETYTWO DOCUMENTS DISAGREEM&E drawings rev CBMS controller, floor 14BMS point scheduleAbbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Functional performance testing

    The Cx authority signs off on evidence, not on a walk-through and a handshake.

    Functional performance tests, integrated systems tests and seasonal commissioning runs are recorded against the asset and the sequence of operations they are proving, with values and setpoints captured where the work happens.

    Fire alarm cause-and-effect testing, smoke control activation and lift recall interfaces are held as their own record set, because they usually gate the fire strategy sign-off as well as PC.

    Open findings from FPT stay attached to the asset with an owner, which stops a system being marked complete on the strength of a tick box.

    Floor 14 — handover ladderEach certificate issues only from signed records beneath itICInstallation completeRecords signed 04 MarContainment inspections212 / 212 signedFCU installation recordscompleteFTFunctional testIn test — booked with BMS contractorLoop checks closed18 / 18Power and BMS liveconfirmedWHWitnessed handoverPunch open — 5 itemsBlocking punch5 openFire alarm cause and effectnot witnessed

    Handover and soft landings

    The building is handed to a facilities team that will run it for the next twenty-five years.

    O&M manuals, as-built schedules, warranty registers and commissioning certificates all need to sit against the same asset that the FM team will search for on day one of occupation.

    Because the dossier builds continuously against the register, a soft landings handover pack is an export rather than a scramble in the final week of the programme.

    Every signature keeps a name, role and timestamp, which is what LEED and BREEAM Cx credit submissions and defects liability disputes both rely on later.

    AUDIT QUERYAHU-04Tower B · level 12-14 · air handling unitFull history retrieved in one queryINSTMechanical installationMEP contractor08 FebDUCTDuctwork leakage testDuctwork sub19 FebIOControls point checkoutControls engineer02 MarFUNCFunctional performance testCommissioning engineer14 MarCERTIFICATEWHWitnessed handover22 MarBuilding services managerPrerequisites demonstratedThe tenant handover pack exports per floor on the day it is signed.

    Seasonal commissioning

    A BMS point-checked in October still has to prove its cooling sequence in July.

    The Cx process specified under the BSRIA and CIBSE Commissioning Codes does not end at practical completion: heating, cooling and free-cooling sequences on the AHUs and chillers have to be re-proven under the seasonal load they were designed for, often eight or twelve months after the tenant has already moved in.

    Landlords and Cx authorities lose track of seasonal commissioning obligations precisely because the team that ran the original FPTs has demobilised by the time the second season arrives, and the outstanding tests live in a closing report nobody reopens.

    Deskely keeps seasonal commissioning as an open, dated obligation against the same AHU, chiller and BMS sequence tags used at PC, so a winter test that was deferred in a summer handover shows up as outstanding rather than forgotten.

    LEED / BREEAM Cx CREDIT EVIDENCECommissioning authority exportEVIDENCE BUNDLE, EXPORTED PER SYSTEMFPT records with setpoint and result, timestampedIST records tying BMS, fire and HVAC togetherSeasonal commissioning run, second seasonO&M manual cross-referenced to the same asset tagCREDIT SUBMISSION STATUSFundamental commissioning, all systemsEnhanced commissioning, seasonal testEnvelope commissioning, façade testing2 of 3Cx credit categories ready for submissionThe credit bundle is an export from the same register that ran commissioning.

    Evidence

    The office fit-out dossier

    A commercial fit-out closes on a set of test sheets and balancing reports tied to floor and tenant, not a narrative. The dossier below is what a landlord or occupier actually checks before signing practical completion.

    RECORDS PRODUCED6 typesAir balancing report (AABC/NEBB…After ductwork pressure test, before TAB…Water balancing reportAfter flushing and before controls…Fire alarm cause-and-effect matrix…Prior to fire officer witness testSmoke control integrated systems…Late-stage integrated test, ahead of…BMS point-to-point verification…Before functional performance testingLEED/BREEAM commissioning reportCompiled for certification submission…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Air balancing report (AABC/NEBB proforma)

    Each terminal unit and diffuser delivers design airflow within tolerance, floor by floor

    After ductwork pressure test, before TAB sign-off

    Water balancing report

    Chilled and heating water circuits achieve design flow rates at each coil and riser

    After flushing and before controls commissioning

    Fire alarm cause-and-effect matrix sign-off

    Every detector, call point and interlock triggers the correct output against the approved matrix

    Prior to fire officer witness test

    Smoke control integrated systems test record

    AOVs, smoke curtains and pressurisation fans operate together on the correct fire scenario

    Late-stage integrated test, ahead of practical completion

    BMS point-to-point verification schedule

    Every BMS point reads and commands correctly against the I/O schedule

    Before functional performance testing

    LEED/BREEAM commissioning report

    Design intent, functional testing and O&M training satisfy the credit's documentary requirements

    Compiled for certification submission after handover

    How it runs

    From shell and core to a tenant moving in.

    Office fit-out and base build programmes reward structure set up before the M&E install starts, because PC is the point where every missing test becomes a delay.

    1. 01

      Model the systems

      HVAC, BMS, electrical, fire and life safety modelled as subsystems, each with its own completion path.

    2. 02

      Parse the asset set

      Mechanical schedules, BMS point lists and cause-and-effect matrices drafted into a reviewed asset register.

    3. 03

      Template the test set

      Pre-functional checklists, FPT, TAB and IST defined once per asset type, instantiated across every floor.

    4. 04

      Gate PC on signed evidence

      Practical completion issued per floor from signed records, with snagging categorised and carried into the defects liability period.

    FAQ

    Questions about Commercial offices scopes.