Inter-array, export and terminations

    Cable evidence that stays with the section, long after the vessel has left the field.

    Cables are installed by a marine spread that demobilises quickly, and tested by specialists in stages. Deskely holds the load-out, lay, burial, pull-in, termination and testing evidence against the section it belongs to, so acceptance is a query rather than an archive search.

    Unit of evidence
    Cable section
    Stages
    Load-out to termination
    Testing
    Continuity, IR, VLF, PD
    Gate
    Section energisation
    EXPORT CABLE — KP 0 TO KP 42CABLE SCHEDULE · REV DKP 0KP 6KP 12KP 18KP 24KP 30Depth of lowering exception — 3 itemsJ-tube pull-inTJB-01Landfall68 sectionseach with lay, burial, termination and test evidenceTAG REGISTERAC-A13-A14Array section A13 to A14A-ITR signedEC-KP12-18Export section KP 12–18B-ITR openTJB-01Transition joint bay land…PreservationTRM-A14-INPull-in and termination A…Punch A open68 sectionsunder one system hierarchy

    The problem

    The cable is buried, the vessel is gone, and the evidence is in four systems.

    A single array section passes through load-out, lay, burial, pull-in at each end, jointing or termination, and a testing campaign — often with a different party responsible for each stage.

    The marine contractor reports in daily progress reports, the termination team in its own forms, and the testing specialist issues PDFs. Nothing is filed against the section itself.

    When a fault appears in the first operating year, reconstructing what was proven and when becomes a forensic exercise. Deskely files every stage under the section, in order.

    A TEST PER SECTION, EVERY JOINTArray + export cablingJ1–WTG04WTG04–WTG09WTG09–WTG14Export circuit 1LandfallCable route — pull-ins, joints, terminationsWHAT ONE SECTION NEEDS BEFORE ENERGISATIONMegger insulation resistanceon file, this sectionVLF withstand testmissing for this sectionOTDR trace, fibre coreon file, this sectionJoint bay X-ray recordmissing for this section46joint bays across the array2sections missing a VLF or X-ray recordDeskely holds every cable test against the section and joint it belongs to.

    Setting up the register

    Every section between two assets is its own tagged item.

    The register mirrors the cable schedule: each section runs from one asset to the next, carries its type, length, KP references and both terminations as sub-items.

    Cable schedules and route drawings are parsed into that register rather than retyped, so the as-designed reference is behind each section from day one.

    As-laid positions, depth of lowering results and burial exceptions are recorded against the same section, which is where the operator will look for them years later.

    1 · SOURCE DOCUMENTSCable schedule rev D68 sectionsRoute position list42 km exportTermination drawings136 endsFactory test certificates68 drumsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERAC-A13-A14Array section A13 to A14CIRCUIT A3EC-KP12-18Export section KP 12–18EXPORTTJB-01Transition joint bay land…LANDFALLTRM-A14-INPull-in and termination A…CIRCUIT A3TWO DOCUMENTS DISAGREECable schedule re…Export section KP 12–18Route position li…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Testing and acceptance

    Continuity, IR and VLF results belong to the section, not to a PDF folder.

    Pre-lay, post-lay and post-termination testing each produce results that matter for a different reason. Held separately, they are three unrelated documents; held under the section, they are a chain that shows nothing degraded between stages.

    Deskely records each test as a signed record with values, instrument reference and the person who took it, so a comparison across stages is possible without opening anything.

    Where a specialist issues its own report, that report attaches to the same section and can be required before energisation.

    SECTION ACCEPTANCE ALONG THE ROUTEExport cable EC-1 · 0 km → 62 km0–14 km14–28 km28–40 km40–52 km52–62 kmLay · bury · pull-in · terminate · test · energiseCable lay and burial depth reportsCable-lay vessel94%Jointing bay and termination recordsJointing contractor76%DC and AC withstand test resultsTesting vendor58%Fibre continuity and monitoring systemOEM commissioning34%Energisation and load acceptanceOperator6%A section is accepted on its own evidence set — not on a route-wide average.

    Energisation

    A string energises when its cables can prove it, and not before.

    Energising a string depends on every section in it: terminations complete, testing passed, earthing proven and no open Category A punch on the run.

    Because sections are tagged and linked to the assets they connect, Deskely can show which single section is holding a string rather than reporting the string as generally incomplete.

    After energisation, the same records become the baseline that any future fault, repair or cable replacement is measured against.

    Section KP 12–18 — acceptanceEvery section carries the same evidence setLAYLay and burial acceptedBlockedDepth of lowering3 exceptionsAs-laid survey filedcompleteTRMTermination completeReadyPull-in recordssignedJointing recordssignedTSTElectrical test acceptedAwaiting LAYIR and continuitysignedVLF withstandnot started

    Burial depth and as-laid survey

    A cable is accepted on where it actually lies, not on where the route drawing said it would.

    Post-lay survey produces a depth-of-lowering profile along the whole route, and every stretch that fails to reach the target burial has to be explained, remediated with rock or mattress protection, or accepted with a deviation the owner and the insurer both sign.

    Crossings with third-party cables and pipelines carry their own agreements and separation requirements, and free spans found on survey have to be dispositioned before the route is closed out.

    Holding the as-laid survey, the burial performance, the crossings and the protection installed against the same cable sections as the electrical test records means route acceptance is one status — and the operator inherits a route it can re-survey against a known baseline.

    AS-LAID BURIAL DEPTH VS DESIGNDepth of lowering profileDesign minimum 1.2 m DoLKP 0 to KP 38 — export cable route, chainage on the horizontal axisFree span, KP 12.4CROSSINGS AND PROTECTION — AS-BUILTInterconnector crossing, rock placementFibre route crossing, concrete mattressFree span KP 12.4 — remediation pendingShore landing duct and transition joint bay38 kmexport route surveyed as-laid1free span open for remediationSurvey vs design overlay generated from the touchdown log, not redrawn by hand.Cable protection is proven metre by metre, against the design, not on average.

    The cable route dossier

    A cable is proven twice — as installed, and again as terminated — and both records have to survive to takeover.

    Burial depth, pull tension and termination each matter to a different party years apart. Deskely ties every cable record to the route section it belongs to, so a fault years later can be checked against the original installation and test evidence rather than a memory.

    RECORDS PRODUCED6 typesCable pull-in and lay tension…During cable lay and pull-in at each…As-laid burial depth and route…Immediately after burial, before route…Joint bay and offshore termination…At each joint bay and at both cable…VLF and HV withstand test resultAfter termination, prior to…TDR and sheath integrity baselineAt final acceptance of the cable, before…Cable route taking-over…At handover of the cable route from…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Cable pull-in and lay tension record

    The cable was installed within the manufacturer's maximum pull tension and minimum bend radius along its route.

    During cable lay and pull-in at each end, offshore substation and turbine.

    As-laid burial depth and route survey

    Target burial depth of protection was achieved along the route, or exceptions are logged against the assessment that accepted them.

    Immediately after burial, before route sign-off.

    Joint bay and offshore termination record

    Factory or field joints and terminations were made to the jointing procedure and passed the associated cure and pressure checks.

    At each joint bay and at both cable ends.

    VLF and HV withstand test result

    The cable insulation withstands the specified test voltage without breakdown before it is permitted to carry load.

    After termination, prior to energisation.

    TDR and sheath integrity baseline

    A reference trace and sheath test are captured for the as-commissioned cable, forming the baseline for future fault location.

    At final acceptance of the cable, before handover.

    Cable route taking-over certificate with punch carried at takeover

    All lay, burial, jointing and test records for the route are signed, with any residual protection or crossing punch listed against an owner.

    At handover of the cable route from installer to owner.

    How it runs

    From cable schedule to an energised string.

    Cable scopes are linear and stage-based. Structuring the register around sections rather than campaigns is what keeps the evidence usable after demobilisation.

    1. 01

      Import the cable schedule

      Each section created as a tagged item with type, length, route reference and both end terminations.

    2. 02

      Record load-out and lay

      Drum load-out, lay progress, as-laid position and any route deviation captured against the section.

    3. 03

      Capture burial evidence

      Depth of lowering results and burial exceptions filed under the section with survey references.

    4. 04

      Sign pull-in and termination

      Pull-in at each end, jointing or termination and earthing recorded per end with photos.

    5. 05

      Log testing at every stage

      Continuity, insulation resistance, VLF or partial discharge results held as signed records with values.

    6. 06

      Gate string energisation

      The string cannot be certified until every section in it has passed testing and cleared blocking punch.

    FAQ

    Questions about Array and export cables scopes.

    Ready to digitize
    commissioning and
    handover?

    We use cookies to improve your experience.
    You can opt out of certain cookies.
    Find out more in our privacy policy.