O&M takeover, warranty period and MCR campaigns

    The evidence does not stop at takeover — the warranty period is where it gets used.

    After takeover, the same register carries end-of-warranty inspections, defect claims and major component replacement campaigns. Deskely keeps the construction evidence and the operating evidence in one place, which is what makes a warranty claim provable.

    Milestones
    PAC then FAC
    Window
    Typically 2 to 5 years
    Use
    Defect claims and MCR
    Basis
    Construction evidence
    FLEET — WARRANTY PERIOD YEAR 2PAC PUNCH AND OBLIGATIONSC08GB-3312Major component replacementPACIssued, 4 carriedEOWInspection year 2FACBlocked — 3 itemsWarranty period — 5 years, 62 assetsTAG REGISTERC08-WTG-GBXGearbox serial GB-3312A-ITR signedC08-BLD-02Blade position 2B-ITR openC08-PAC-114Carried PAC item 114PreservationC08-EOW-01End-of-warranty inspectionPunch A open62 positionsunder one system hierarchy

    The problem

    The claim depends on records written three years earlier.

    When a component fails inside the warranty period, the argument is about what was installed, how it was torqued, whether it was preserved and what was accepted at takeover.

    If that evidence sits in a scanned archive owned by a contractor who has demobilised, the claim is settled on commercial pressure rather than on fact.

    Deskely keeps the construction record live and searchable at the asset, so the operations team argues from the record instead of around it.

    WHO OWNS WHICH DEFECT24 month defects notification periodTaking-overWarranty expiry — month 24Month 17 — todayOPEN DEFECT CLAIMSBlade leading-edge erosion, WTG-07raised within windowOEMGearbox oil analysis flag, WTG-19raised after the window closedOwnerYaw bearing grease leak, WTG-22raised within windowDisputedConverter cabinet corrosion, WTG-31raised within windowOEM1claim raised after the DNP window closed1defect disputed between OEM and ownerDeskely timestamps every defect against the taking-over date it is measured from.

    Provisional and final acceptance

    PAC and FAC are certificates with conditions attached.

    Provisional acceptance usually carries a punch list and a set of outstanding obligations. Final acceptance closes them.

    Deskely holds both as certificates issued per asset from the underlying records, with the carried items owned, dated and visible to both parties throughout the period.

    Nothing quietly disappears between PAC and FAC, because the list is the same list the whole time.

    Position C08 — acceptance milestonesPAC carries obligations; FAC closes themPACProvisional acceptanceIssued 18 OctCommissioning set signedcompleteCategory A punchclearedEOWEnd-of-warranty inspectionScheduledInspection template issued84 checksAccess and access planagreedFACFinal acceptanceBlockedCarried PAC items3 openWarranty claim C08-01in dispute

    End-of-warranty inspections

    The inspection campaign is the last chance to move cost back across the line.

    End-of-warranty inspections run across the fleet on a fixed template, offline, with photos — the same execution model as construction.

    Findings are raised as punch against the asset and linked to the original installation record where relevant, which is what turns a finding into a claim.

    Fleet-level reporting shows how many assets have been inspected, what was found and what remains contested.

    DEFECT LIFECYCLE CLOCKWarranty year 3 of 5 · Array BDEF-0442 Blade leading edge erosionRaised Day 4 · claim deadline Day 3462% of windowDEF-0451 Yaw bearing grease sample failRaised Day 6 · claim deadline Day 2188% of windowDEF-0459 Gearbox oil particle countRaised Day 9 · claim deadline Day 3912% of windowDEF-0433 Cable termination hot spotRaised Day -2 · claim deadline Day 13ClosedDEF-0461 Pitch system fault codeRaised Day 11 · claim deadline Day 264% of window2defects inside the final 25% of window0claims missed on a filing deadlineEvery defect clock runs against the warranty deed, not a spreadsheet guess.

    Major component replacement

    A blade or gearbox exchange is a small commissioning project.

    MCR campaigns need the same discipline as installation: component traceability, lift and torque records, functional testing and a return-to-service decision backed by evidence.

    Deskely runs them as scoped campaigns against the existing asset register, so the replacement record joins the asset's history rather than starting a new file.

    Years later, the asset shows what was original, what was replaced, when and on whose signature.

    AUDIT QUERYC08-WTG-GBXGearbox GB-3312 — failed in year 2Claim evidence assembled in one queryITR-ADrivetrain installation recordInstallation technician11 May Y0PRSOil circulation historyPreservation routineY0–Y1EOWYear 2 inspection findingO&M inspector07 Jun Y2CERTIFICATECLMWarranty claim C08-01submittedOwner's asset managerPrerequisites demonstratedThe claim is argued from the record instead of around it.

    Availability and serial defect campaigns

    The warranty is settled on numbers, so availability and defect evidence has to be defensible month by month.

    A service agreement warrants an availability figure, and the difference between the warranted and the achieved number is a payment. Getting there means agreeing downtime categorisation turbine by turbine, event by event: OEM fault, grid curtailment, weather standby, owner-caused outage or force majeure.

    Alongside that sits the serial defect question — once a fault appears on enough positions it becomes a campaign with a different commercial owner, and the threshold argument is won or lost on how consistently the individual events were recorded.

    With defect records, categorisation and evidence held against each position from the day it was taken over, the monthly availability report and the serial defect case are built from the same signed history both parties already accepted.

    AVAILABILITY AGAINST WARRANTYOperations and warranty periodWarranted availability 96.5%JFMAMJNDMonthly time-based availability, full array, rolling 8 monthsOPEN SERIAL DEFECT CAMPAIGNSPitch bearing grease leak, batch B411 turbinesYaw motor overheat trip, batch A24 turbinesConverter cooling fan bearing wearclosed, all units97.0%trailing 12-month availability2serial defect campaigns open across the fleetAvailability and defect reporting draw from the same event log the O&M crew close.The warranty conversation runs on figures both parties already trust.

    The warranty baseline

    Performance is judged against a baseline, and the baseline is only defensible if it was recorded, not remembered.

    Availability and power curve disputes in year two are argued from records taken at warranty start, not from the punch list. Deskely keeps every warranty-relevant record against the asset from the day it was signed, so the baseline the operator inherits is the one the OEM actually tested.

    RECORDS PRODUCED6 typesPower curve and performance test…During the warranty start test campaign,…SCADA point-to-point verificationImmediately before warranty start is…Yaw and pitch system calibration…During the warranty start test sequence.Vibration and condition monitoring…At warranty start, before the asset…Preservation and lay-up completion…At the transition from installation to…Warranty start certificate with…At the formal start of the warranty…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Power curve and performance test record

    The turbine's measured output against wind speed matches the contracted power curve within the agreed tolerance.

    During the warranty start test campaign, after commissioning is complete.

    SCADA point-to-point verification

    Every operational and alarm signal used for availability calculation reaches the operator's system correctly, forming the baseline for future disputes.

    Immediately before warranty start is declared.

    Yaw and pitch system calibration record

    Yaw and pitch actuation are calibrated to the control system's reference positions at warranty start.

    During the warranty start test sequence.

    Vibration and condition monitoring baseline

    Drivetrain and tower vibration signatures are captured as the reference condition against which future degradation is measured.

    At warranty start, before the asset enters normal operation.

    Preservation and lay-up completion record

    All preservation routines run since mechanical completion were closed out before the warranty clock started, ruling out lay-up damage as a cause of later failure.

    At the transition from installation to operational status.

    Warranty start certificate with punch carried at takeover

    The performance, calibration and monitoring baseline is signed and any residual punch is listed with an owner and a close-out date.

    At the formal start of the warranty period.

    How it runs

    From takeover to final acceptance and beyond.

    The operating organisation inherits an asset base and a set of obligations. Both are easier when the construction evidence never left the system.

    1. 01

      Issue takeover per asset

      PAC certificates from signed records, with outstanding items carried, categorised and owned.

    2. 02

      Carry the punch list live

      Outstanding obligations tracked in the same register as construction, visible to both parties.

    3. 03

      Run inspection campaigns

      Templated end-of-warranty inspections across the fleet, executed offline with photos.

    4. 04

      Link findings to records

      Each finding tied to the installation or commissioning record it disputes, forming the basis of a claim.

    5. 05

      Execute MCR as a campaign

      Component traceability, lift, torque and functional testing recorded against the existing asset.

    6. 06

      Close out at final acceptance

      FAC issued when carried items are closed, with the full history exportable for the asset owner.

    FAQ

    Questions about Operations and warranty scopes.

    Ready to digitize
    commissioning and
    handover?