Landfall, onshore cable and point of connection

    Completions software for the onshore scope that decides whether the wind farm can export at all.

    Landfall, onshore cable route, the onshore substation and the point of connection are usually delivered by different contractors against a grid connection date that cannot move. Deskely holds the whole onshore chain in one register with the connection conditions as gates.

    Scope
    Landfall to point of connection
    Parties
    Civil, cable, HV, TSO
    Driver
    Fixed connection date
    Gate
    Compliance and energisation
    ONSHORE SUBSTATION — BAY 220 kVCONNECTION CONDITIONS · REV BTJB-02LandfallJBJBJBJB18 km onshore routeBAY 01BAY 02BAY 03Onshore substationPoint of connection2 CONNECTION CONDITIONS UNEVIDENCEDTAG REGISTERSS-BAY-02220 kV feeder bay 2A-ITR signedTJB-02Transition joint bay 2B-ITR openSS-ERT-GRDSubstation earthing gridPreservationSS-MET-01Settlement meteringPunch A open520 tagsunder one system hierarchy

    The problem

    Four contractors, one connection date, and one set of conditions to satisfy.

    Civils, cable installation, substation build and HV commissioning each run to their own programme, and the transmission operator has conditions that apply across all of them.

    When the connection date approaches, the question is not who is behind — it is which specific condition is unevidenced. That answer usually lives in four different reporting formats.

    Deskely puts the onshore chain in one register so the connection conditions can be tracked as prerequisites rather than as a checklist someone owns in a document.

    MULTIPLE EXTERNAL WITNESSES, ONE GATEOnshore substation + grid connectionGrid code compliance evidence converging on a single energisation dateTSO / DNOEnergisation permissionIndependent engineerGrid code complianceProtection specialistRelay setting sign-offONE ENERGISATION DATE, THREE SIGN-OFFS NEEDED612 grid code test records held across three organisationsOUTSTANDING BY WITNESSTSO / DNO0 openIndependent engineer3 openProtection specialist1 openEvery record traced to the compliance clause it satisfiesDeskely tracks each external witness's sign-off against the same energisation date.

    Setting up the register

    Landfall, route and substation belong to one continuous scope.

    Transition joint bays, duct sections, link boxes, the substation bays, transformers, earthing grid, protection and SCADA are modelled as tagged assets on one route from the sea to the grid.

    Cable schedules, SLDs and route drawings are parsed into that register so nothing is retyped and every asset keeps its drawing reference.

    The result is a scope that can be reported end to end rather than as three unrelated packages.

    1 · SOURCE DOCUMENTSSubstation SLD rev B520 tagsOnshore route drawings18 kmJoint bay and link box s…46 itemsSCADA signal list1 240 signalsPARSE + MATCHtag · description · drawing ref2 · ONE TAG REGISTERSS-BAY-02220 kV feeder bay 2BAY 02TJB-02Transition joint bay 2LANDFALLSS-ERT-GRDSubstation earthing gridEARTHSS-MET-01Settlement meteringMETERTWO DOCUMENTS DISAGREESubstation SLD re…Transition joint bay 2Onshore route dra…Abbreviated descriptionEngineer picks the sourcedecision loggedWeeks of transcription become a draft an engineer reviews.

    Compliance testing

    Grid code evidence is not paperwork — it is the permission to export.

    Protection coordination, earthing measurements, SCADA signal lists, metering accuracy and compliance test results all feed the connection agreement conditions.

    Each is held as a signed record against the asset it belongs to, with the condition it satisfies referenced, so the compliance pack builds itself as the work is done.

    When the operator asks for evidence against a specific condition, the answer is a filtered view rather than a document search.

    GRID CODE COMPLIANCE PROGRAMMEGrid connection GSP-14TSO HOLD POINTS BEFORE ENERGISATIONFault ride-through test resultsReactive power capability curveFrequency response validationBlockingProtection settings sign-offSCADA and telemetry acceptanceBlockingPROJECT SIDE ⟷ TSO SIDECompliance test reportsBilateral agreement clausesProtection and control recordsConnection offer conditionsPunch category AOperational notifications2hold points left before energisation100%of records exported to the TSO portalEnergisation is authorised from the compliance evidence set, not a verbal all-clear.

    Energisation

    Energisation is granted against evidence, and withdrawn against gaps.

    The energisation certificate is gated on earthing, protection, interlocks, safety systems and any outstanding Category A punch on the affected bays.

    Deskely will not issue while those are open, and shows exactly which record or item is holding the gate.

    Once energised, the same evidence becomes the baseline for the operations team and for any future modification.

    Point of connection — energisationThe connection agreement conditions are the prerequisitesCIVCivil and cable acceptanceIssued 21 MayDuct and joint bay recordssignedCable test resultssignedCMPCompliance testingBlockedProtection coordinationin progressEarthing measurementsignedENEnergisationAwaiting complianceSCADA signals proven64%Category A punch2 open

    The grid code compliance dossier

    The connection is granted on a dossier, and the transmission operator reads it long after the contractors have left.

    Reactive capability demonstrated across the P-Q envelope, fault ride-through evidence, power quality and harmonics measurement, frequency and voltage control response, protection coordination and the SCADA points list proven end to end with the control centre: each is a compliance item with an owner and a deadline.

    Compliance evidence is generated across energisation, first export and a monitoring period that can run months past practical completion, and it is usually assembled by whoever is left rather than by whoever ran the test.

    Tracking compliance items as records against the connection asset means the dossier builds as the tests are witnessed, and the final submission to the transmission operator is an export rather than a hunt through three contractors' archives.

    GRID CODE COMPLIANCE DOSSIERSubmitted to the TSOCOMPLIANCE TEST RESULTSReactive capability envelope at POC±0.33 pfLow voltage fault ride-through0% for 140 msPower quality — flicker and harmonicswithin limitsFrequency response — FFR and inertiaunder reviewVoltage step response testpending witnessSCADA POINTS LIST — POINT OF CONNECTIONActive and reactive power, 4 second resolutionCircuit breaker and disconnector statusTransformer tap position and alarmsEvent and disturbance recorder extracts1dossier, one point of connection agreement2compliance tests remaining before final acceptanceThe TSO reads a single evidence set, version-controlled from first energisation.

    The connection dossier

    The transmission operator reads one file, built from records that were never generated by the same contractor.

    From landfall to the point of connection, four organisations each hand over a slice of evidence. Deskely gathers it against one asset chain, so the connection agreement's conditions can be checked off against signed records instead of a document search under deadline.

    RECORDS PRODUCED6 typesTransformer and switchgear bolt…During substation electromechanical…Cable termination and jointing…Along the onshore cable route, before…VLF and HV withstand test resultBefore the substation is permitted to…Earthing and protection…During substation commissioning, ahead…SCADA point-to-point verification…During commissioning, before…Substation taking-over certificate…At handover of the substation from…DOSSIERIndexed persubsystem and tagExport readyEach record lands in the same structure, so the dossier assembles itself.

    Transformer and switchgear bolt torque record

    Structural and busbar connections in the substation were made up to specification during erection.

    During substation electromechanical assembly.

    Cable termination and jointing record

    Onshore export cable and duct sections were jointed and terminated to the cable schedule at each transition joint bay.

    Along the onshore cable route, before backfill and reinstatement.

    VLF and HV withstand test result

    Cable and switchgear insulation withstands the specified test voltage ahead of first energisation.

    Before the substation is permitted to energise.

    Earthing and protection coordination test record

    Earth grid resistance and protection relay settings meet the design and the connection agreement's requirements.

    During substation commissioning, ahead of the compliance test programme.

    SCADA point-to-point verification with the control centre

    Every signal required by the connection agreement reaches the transmission operator's control room correctly mapped.

    During commissioning, before energisation is requested.

    Substation taking-over certificate with punch carried at takeover

    All civil, cable and HV commissioning records are signed, with any remaining Category B punch listed against an owner ahead of energisation.

    At handover of the substation from contractor to owner.

    How it runs

    From duct sections to an energised point of connection.

    Grid connection scopes are date-driven and condition-driven. Structuring the register around the conditions is what keeps the last three months calm.

    1. 01

      Model the onshore route

      Landfall, transition joint bays, duct sections, link boxes and the substation as one tagged chain.

    2. 02

      Map the connection conditions

      Each condition of the connection agreement tied to the records that will evidence it.

    3. 03

      Capture civil and cable evidence

      Duct installation, cable pulling, jointing and link box records signed against the section.

    4. 04

      Commission the substation

      Bay by bay: transformer, protection, earthing, SCADA and metering with signed site test records.

    5. 05

      Run compliance testing

      Protection coordination, earthing measurement and compliance tests recorded against the assets they prove.

    6. 06

      Issue energisation

      The certificate issues only when every prerequisite is signed and blocking punch is cleared.

    FAQ

    Questions about Onshore substations and grid connection scopes.

    Ready to digitize
    commissioning and
    handover?