Management of change (MOC): process, steps and engineering change
Deskely Completions team Singapore
Management of change (MOC) is the process that makes sure a change to a plant, its equipment, its procedures or its organisation is reviewed for hazards, approved, and reflected in the drawings, procedures and training before it is put into use. Many serious process accidents have started with a change that nobody reviewed.
This guide covers what counts as a change, the MOC process step by step, what OSHA process safety management requires, temporary and emergency changes, and how engineering change works on projects, where every drawing revision ripples into the completions records.
- Any change that is not a replacement in kind goes through MOC: equipment, chemicals, technology, procedures, organisation.
- MOC means: request, assess hazards, review, approve, implement, update documents, train, verify, close.
- OSHA 29 CFR 1910.119(l) requires written MOC procedures; a pre-startup safety review follows significant changes.
- On projects, a drawing revision can invalidate signed inspection records. Trace every change to what it touches.
What is management of change?
Management of change is a formal procedure for proposing, assessing, approving, implementing and closing out changes. It is one of the core elements of process safety management, alongside process safety information, process hazard analysis, operating procedures, mechanical integrity and pre-startup safety review.
The goal is simple: no change goes into service without someone competent asking what could go wrong, deciding it is acceptable, and making sure the drawings, procedures and people are updated to match.
What counts as a change?
| Type | Examples |
|---|---|
| Equipment and facilities | New or modified piping, a different valve type, new tie-ins, removed equipment, bypasses |
| Process and technology | New feedstock or chemical, changed operating limits, new set points, altered control or trip logic |
| Procedures | Changed operating, maintenance or emergency procedures |
| Software and control systems | Changes to DCS or safety system logic, alarm settings, overrides |
| Organisation and people | Changes to staffing levels, roles, shift patterns or contractors in safety-critical positions |
| Temporary changes | Temporary repairs, clamps, temporary hoses, jumpers and overrides |
A replacement in kind (an identical part, or one that meets the same design specification) is not a change and does not need MOC. Deciding what is and is not "in kind" is itself part of a good MOC procedure.
The MOC process step by step
- 01Raise the request
Describe the change, the reason, the technical basis and the systems affected.
- 02Classify it
Permanent, temporary (with an expiry date) or emergency; minor or major. The class sets how deep the review goes.
- 03Assess the hazards
A checklist, what-if, HAZID or HAZOP as the change demands, covering process safety, occupational safety, environment and operability.
- 04Review by the disciplines
Process, mechanical, electrical, instrument, operations and safety review the change and set conditions.
- 05Approve
Authorised approvers sign off, at the level the classification requires.
- 06Implement
The change is made under the normal work permit and quality controls.
- 07Update documents
P&IDs, process safety information, datasheets, procedures, alarm and trip schedules and maintenance plans are updated.
- 08Train and communicate
Operators and maintenance staff affected by the change are informed and trained before it is used.
- 09Pre-startup safety review
For significant changes, a PSSR checks construction, procedures, training and PHA actions are complete before start-up.
- 10Close out
All actions are closed, documents issued, and temporary changes removed or made permanent by their expiry date.
OSHA process safety management requirements
In the US, OSHA's process safety management standard (29 CFR 1910.119) requires employers covered by it to have written MOC procedures for changes to process chemicals, technology, equipment, procedures and facilities that affect a covered process (paragraph l). The procedures must address:
- The technical basis for the change.
- The impact of the change on safety and health.
- Modifications to operating procedures.
- The time period for the change.
- Authorisation requirements for the change.
Employees affected by the change must be informed and trained before start-up, and process safety information and procedures must be updated. Paragraph (i) requires a pre-startup safety review for new facilities and for modified facilities when the change is significant enough to require a change in the process safety information. Similar requirements exist elsewhere, for example in the EU Seveso III directive and the UK COMAH regulations.
Temporary and emergency changes
Temporary changes are the weak spot of many MOC systems: a temporary clamp or bypass that is still there years later, never reviewed as permanent. A temporary MOC carries an expiry date, an owner and a removal plan, and is tracked until it is removed or converted into a permanent change through the full process.
Emergency changes, made to keep the plant safe when there is no time for the full review, get a minimum review at the time and the full review immediately afterwards.
Engineering change on capital projects
During design and construction, the same idea runs through different names: technical queries (TQs), site queries, field change requests, design change notices and engineering change requests. Each change ends up as a drawing revision, and each revision can change tags that already have work done against them.
- A signed inspection record may have been made against the old revision and need repeating.
- A punch item may be resolved by the change, or a new one may be needed.
- A test pack may need its line list, limits or spades updated, and possibly a re-test.
- A commissioning procedure may have steps that no longer match the P&ID.
Finding all of that by comparing revisions by eye is slow and things get missed. The impact of each revision has to be traced tag by tag before anyone signs against the old drawing. See how to read a P&ID.
Good MOC practice
- Make it easy to raise a change, so people do not work around the system.
- Scale the review to the risk: a simple checklist for minor changes, a HAZOP for major ones.
- Link each MOC to the documents and tags it affects, so updates are not forgotten.
- Track temporary changes to their expiry dates.
- Review open MOCs regularly and audit closed ones for quality.
The Deskely products for this
Frequently asked questions
What is management of change?
A formal process for reviewing, approving and documenting changes to a plant, its equipment, procedures or organisation before they are implemented, so that the hazards are identified and controlled.
What is the MOC process?
Raise the request, classify it, assess the hazards, review it with the disciplines, approve it, implement it, update the documents, train the people affected, carry out a pre-startup safety review if needed, and close it out.
What is a replacement in kind?
A replacement that meets the design specification of the item it replaces, such as an identical part. It does not need management of change.
Which OSHA standard covers management of change?
OSHA 29 CFR 1910.119, process safety management of highly hazardous chemicals, paragraph (l). Pre-startup safety review is paragraph (i).
What is a temporary MOC?
A change approved for a limited time, with an expiry date and a plan to remove it or make it permanent through the full MOC process.
How does MOC apply to drawing changes?
A drawing revision is a change: its impact on inspection records, punch, test packs and procedures must be traced and dealt with before anyone works to the new revision.