Commissioning checklist: free template from mechanical completion to handover
Deskely Completions team Singapore
A commissioning checklist tracks everything a system or subsystem needs between the end of construction and handover: the certificates, the tests, the procedures and the sign-offs. It is the one page that tells you whether a subsystem is really ready for its next milestone.
This page gives you a free commissioning checklist in Excel and PDF, organised by phase, and explains how to use it, how it relates to ITRs and procedures, and what changes when you have hundreds of subsystems instead of one.
- Use one checklist per subsystem, the unit commissioning works in.
- It runs through four phases: mechanical completion, pre-commissioning, commissioning and handover.
- Each line points to the record that proves it: an ITR, a test pack, a certificate.
- The checklist summarises; the evidence lives in the records behind it.
What is a commissioning checklist?
A commissioning checklist is a list of the conditions a system or subsystem must meet at each stage of completion, with a status, a reference to the record that proves each one, and sign-off at the end. It is used by the commissioning lead to plan the work, by the team to see what is still open, and by the owner to accept the subsystem.
It works at a higher level than an inspection and test record. An ITR records one check on one tag; the commissioning checklist confirms that all the ITRs, tests and certificates for the subsystem are done.
The checklist, phase by phase

Mechanical completion. A ITRs signed, pressure test packs closed and reinstated, flushing, cable and insulation resistance tests, equipment and instrument installation, insulation and coatings, A punch closed, redlines submitted, and the mechanical completion certificate signed.
Pre-commissioning. Loop checks, motor solo runs, relay testing, valve stroke and function tests, safety valves set and locked, lubrication and first fills, B ITRs signed, and the ready for commissioning certificate.
Commissioning. Procedures approved, permits and isolations, utilities available, control and safety logic tested against the cause and effect, fire and gas tested, functional tests, training, the pre-startup safety review where required, and the ready for start-up certificate.
Handover. Remaining punch agreed with the owner, the handover dossier complete, spares and special tools handed over, and the handover certificate signed.
How to use it
- 01One sheet per subsystem
Copy the sheet for each subsystem and fill in the project, system and subsystem at the top.
- 02Tailor the checks
Remove checks that do not apply and add discipline-specific ones from your completions procedure. Mark the rest N/A rather than deleting them, so the reviewer can see they were considered.
- 03Point to the evidence
For each check, enter the record that proves it: the ITR numbers, test pack, certificate or report.
- 04Update the status as you go
Set Done, Open or N/A. The counts at the top update automatically.
- 05Sign it off at each milestone
Construction, commissioning and the owner sign when the subsystem is handed over.
Building and HVAC commissioning checklists
Building commissioning uses the same idea under different names. Pre-functional checklists confirm each piece of equipment (air handlers, chillers, pumps, VAV boxes) is installed and started up correctly; functional performance tests then prove each system works through its sequences of operation. Guidance such as ASHRAE Guideline 0 describes the process. The structure of the template above, phases, checks, evidence and sign-off, works for both.
For mission-critical buildings, see data centre commissioning and its five commissioning levels.
When one checklist becomes hundreds
A spreadsheet checklist works for a handful of subsystems. On an industrial or offshore project with hundreds of subsystems and tens of thousands of tags, the problem changes: the checklist is only as current as the last time someone counted the ITRs, punch items and test packs behind it, and every subsystem's status is a manual roll-up.
In Deskely, the checklist is computed from the records themselves: every ITR, punch item, test pack and certificate is held against its tag and subsystem, so each subsystem's readiness for MC, RFC, RFSU and handover is live, and the dossier behind it is already assembled.
The Deskely products for this
Frequently asked questions
What is a commissioning checklist?
A list of the conditions a system or subsystem must meet from mechanical completion to handover, with the status of each, the record that proves it, and sign-off.
What is the difference between a commissioning checklist and an ITR?
An ITR records one inspection or test on one tag. A commissioning checklist confirms, at subsystem level, that all the ITRs, tests and certificates needed for each milestone are complete.
What should a commissioning checklist include?
Mechanical completion checks, pre-commissioning tests, commissioning prerequisites and tests, and handover items, each with a reference to its evidence and a sign-off.
Is the template free to use?
Yes. Download the Excel or PDF version and adapt it to your project and completions procedure.
What is a pre-functional checklist?
In building commissioning, a checklist confirming a piece of equipment is installed and started up correctly before its functional performance test.