Commissioning report template: free system commissioning report (Excel and PDF)

Deskely Completions team Singapore

A commissioning report closes out the commissioning of a system: what was commissioned, against which procedure, which tests were run and what they showed, what deviated, and whether the system is ready for the next step.

This page gives you a free commissioning report template in Excel and PDF and explains what each section should say.

Key takeaways
  • State the scope and the boundaries: what was not commissioned matters too.
  • Record each test against its expected result, not only "OK".
  • List deviations and punch items with numbers, so they can be tracked.
  • End with a clear conclusion: ready for start-up, or not, and on what conditions.

What goes in a commissioning report

  1. 01
    Scope

    The system and subsystems commissioned, the boundaries, and anything excluded.

  2. 02
    Prerequisites

    RFC certificates, approved procedure, permits and isolations, utilities, control and safety systems available.

  3. 03
    Tests performed

    Each test with the procedure step, the expected result, the actual result and the record reference.

  4. 04
    Deviations and punch items

    Where the procedure was not followed or results differed, and the punch items raised.

  5. 05
    Conclusion

    Whether the system is ready for start-up, performance testing or handover, and any conditions.

The template

Commissioning report template with system and procedure fields and sections for scope, prerequisites, tests performed with expected and actual results, deviations and punch items, conclusion and sign-off
The free commissioning report: one page per system.

The report summarises; the detail sits in the commissioning procedure, the test records and the punch list. A method statement or procedure comes before it, and the completion certificates after it.

Reports from the records

Writing a commissioning report means pulling test results, punch items and certificates together from several places.

In Deskely, the procedures, test records and punch items already sit against the system's tags, so the evidence for the report is assembled rather than collected.

The Deskely products for this

Frequently asked questions

What is a commissioning report?

The document that records the commissioning of a system: scope, prerequisites, tests and results, deviations and punch items, and whether the system is ready for the next step.

Who writes the commissioning report?

The commissioning engineer responsible for the system, reviewed by the commissioning lead and accepted by the client.

What is the difference between a commissioning report and a commissioning procedure?

The procedure says how the system will be tested. The report records what happened when it was.

Is the template free?

Yes. Download the Excel or PDF version and adapt it to your project.

Writing commissioning reports from scattered records?Deskely holds the procedures, test records and punch items against each system's tags, so the evidence for every commissioning report is already in one place.
  • In production since 2014
  • Thousands of daily users
  • On MODEC FPSO projects since 2016

Autonomous engineering runs on Deskely.

Talk to sales