TEMPLATEResources / TemplatesUpdated 8 Nov 2026 · 5 min read

Management of change (MOC) form: free request, approval and register template (Excel and PDF)

Deskely Completions team Singapore

A management of change (MOC) form is the record that a change to a plant, its equipment, its procedures or its people was described, reviewed for hazards, approved by the right people, reflected in the drawings and procedures, and closed out, before and after the change was put into use. It is the paper trail of process safety management.

This page gives you a free MOC form in Excel and PDF: the request with permanent, temporary and emergency types, the risk review, a checklist of documents to update, training and PSSR, five approval signatures and the close-out. A second sheet is the MOC register, with days open and a flag on every temporary change past its expiry date.

Key takeaways
  • Every change that is not a replacement in kind needs an MOC: equipment, chemicals, set points, procedures, organisation.
  • A temporary change carries an expiry date and is tracked until it is removed or made permanent.
  • The MOC is not closed until the P&IDs, procedures, alarm settings and training match the change.
  • Significant changes get a pre-startup safety review before they go into service.

What the MOC form has to cover

In the US, OSHA's process safety management standard, 29 CFR 1910.119 paragraph (l), requires written MOC procedures for changes to process chemicals, technology, equipment, procedures and facilities. The procedures must address the technical basis for the change, its impact on safety and health, changes to operating procedures, the time period of the change and who authorises it. People affected must be informed and trained before start-up, and the process safety information must be updated. Similar duties sit in the EU Seveso III directive and the UK COMAH regulations.

A good form turns those duties into fields, so nothing depends on memory:

SectionWhat it recordsWhy
The changeDescription, reason and technical basis, tags and drawings affectedThe technical basis, and what exactly is different
TypePermanent, temporary (with expiry date) or emergency; minor or majorSets the depth of review and the time period
Risk reviewWhether a HAZID or HAZOP is needed, the method used, risk ranking before and afterThe impact on safety and health
Documents to updateP&IDs, cause and effect charts, procedures, datasheets, alarm and trip list, relief and flare data, training materialProcess safety information kept true
Training and PSSRWho is trained and how; whether a pre-startup safety review is neededPeople informed and trained before start-up
ApprovalOriginator, area authority, technical authority, HSE, operationsAuthorisation at the right level
Close-outImplementation dates, documents issued, temporary change removed, verificationProof the change was finished, not just approved

Permanent, temporary and emergency changes

TypeMeaningWhat the form asks for
PermanentThe change stays in placeFull review and approval before implementation
TemporaryIn place for a set period: a clamp, a bypass, a temporary hose, a changed set point for a trialAn expiry date (the form flags it if missing) and a removal plan; at expiry it comes out or goes through a new MOC to become permanent
EmergencyMade to keep the plant safe when there is no time for the full reviewA minimum review at the time, the full review straight after

Temporary changes are where MOC systems most often fail: a clamp fitted for three months and still there years later, never reviewed as permanent. The register sheet flags every open temporary change that is past its expiry date, expires within 14 days or has no expiry date at all.

What is in the template

Management of change form template with MOC number, change type and expiry date fields, description and reason, a table of tags affected, and a risk review section with HAZID and HAZOP and risk ranking
The free MOC form, page one. Documents, approval and close-out follow; the register is the last sheet.
SheetFields
MOC requestMOC number, date, revision, facility, systems affected, originator; change type (Permanent, Temporary, Emergency) with expiry date and a warning if a temporary change has none; category (Minor, Major); description; reason and technical basis; tags affected with drawing and what changes (one worked example row)
MOC request (risk review)HAZID or HAZOP needed (Yes, No), review method, risk ranking before and with the change, review reference, hazards and controls
MOC request (documents)Ten document types with update needed, new revision, owner and date done, and a live count of updates needed, done and still to do
MOC request (approval and close-out)Training needed, PSSR required and reference; approval by originator, area authority, technical authority, HSE and operations with a decision drop-down; conditions; implementation, removal, document issue, training and closure dates; close-out verification and signatures
MOC registerOne line per change: number, title, unit, type, category, originator, raised, expiry, approved, implemented, closed, status (Open, Approved, Implemented, Closed, Rejected), days open, temporary change flag, PSSR; counts by status and of temporary changes past expiry

Where MOC fits in the project and plant flow

On an operating plant, the MOC form is the gate for any change to a process covered by process safety management. When the change is significant enough to alter the process safety information, a pre-startup safety review checks that construction, procedures, training and hazard review actions are complete before it is used.

On a capital project the same idea runs through technical queries, field change requests and drawing revisions. Each revision can touch tags that already have signed inspection records, punch items, test packs or procedures against them, and those have to be found before anyone signs against the old drawing. The management of change guide covers the process step by step; see also how to read a P&ID and the cause and effect matrix, two of the documents most often updated by an MOC.

Tracing drawing changes in Deskely

Deskely Delta compares two revisions of a drawing tag by tag and traces every change to the ITRs, punch items and procedures it touches, before anyone signs against the old revision.

The Deskely products for this

Frequently asked questions

What is a management of change form?

The record of one change: what it is and why, the hazard review, the documents and training it affects, who approved it, and how it was implemented and closed out.

Who approves a management of change?

It depends on the procedure and the risk. Typically the area authority and a technical authority for the discipline, with HSE and operations for larger changes. The form has space for five approvers.

What is a temporary MOC?

A change approved for a limited time, with an expiry date. By that date it is removed, or it goes through the full MOC process to become permanent.

Does a replacement in kind need an MOC?

No. A replacement that meets the design specification of the item it replaces is not a change. Deciding what counts as in kind is part of the MOC procedure.

Which OSHA paragraph covers management of change?

OSHA 29 CFR 1910.119, paragraph (l). Pre-startup safety review is paragraph (i).

What does this revision touch that is already signed?Deskely Delta compares two revisions of a drawing tag by tag and traces every change to the ITRs, punch items and procedures it touches, before anyone signs against the old revision.
  • In production since 2014
  • Thousands of daily users
  • On MODEC FPSO projects since 2016

Autonomous engineering runs on Deskely.

Talk to sales