A load break switch can open and close normal load current and also isolates, but cannot clear a fault. It is often combined with fuses.

ANSI / IEEE
IEC 60617 · S00290

What the load break switch symbol means

A load break switch can open and close normal load current and also isolates, but cannot clear a fault. It is often combined with fuses.

ANSI and IEC symbols

ANSI / IEEE 315

Usually drawn as a disconnect switch and marked as load break in its label.

ANSI SVG
IEC 60617S00290

Switch-disconnector; On-load isolating switch. A switch with both the disconnector bar and the switch-disconnector mark at the fixed contact.

IEC SVG

Where you see it

Ring main units, transformer feeders and medium voltage distribution.

What is written next to it

On a one-line, the load break switch carries its tag and its ratings: rated voltage and current, making capacity, and fuse ratings when fused.

What gets checked at commissioning

Before the load break switch is energised, the test records usually cover: contact resistance, operation and interlocks. Each check is recorded against the tag, so the system can be handed over with its evidence. See commissioning software.

Frequently asked questions

What does the load break switch symbol look like?

On ANSI drawings: Usually drawn as a disconnect switch and marked as load break in its label. In IEC 60617: A switch with both the disconnector bar and the switch-disconnector mark at the fixed contact.

Is the load break switch symbol the same in IEC and ANSI?

No. A switch with both the disconnector bar and the switch-disconnector mark at the fixed contact. The IEC 60617 number is S00290.

Where is a load break switch used?

Ring main units, transformer feeders and medium voltage distribution.

Every load break switch on your one-line, tracked to energisation.Deskely holds the tag register, test records and punch items for every electrical tag on your project, through to handover.
  • In production since 2014
  • Thousands of daily users
  • On MODEC FPSO projects since 2016

Autonomous engineering runs on Deskely.

Talk to sales