TEMPLATEResources / TemplatesUpdated 8 Nov 2026 · 3 min read

Start-up checklist: free start-up readiness checklist with Go / No-Go decision (Excel and PDF)

Deskely Completions team Singapore

A start-up readiness checklist is the final Go / No-Go check before a commissioned system is started with its process medium, confirming that procedures are issued, operators trained, category A punch closed, the PSSR done, safety systems tested, isolations cleared and utilities available, and recording the decision with signatures.

This page gives you a free start-up readiness checklist in Excel and PDF, with 15 requirements, a punch line that turns No-Go if any category A item is open, an overall decision that fills in by itself, and a register that shows the decision for every system.

Key takeaways
  • One No-Go on any requirement means the system does not start.
  • Category A punch open on the system must be zero; the template checks it for you.
  • The PSSR and the RFSU certificate come before the Go decision, not after.
  • Operations signs the decision, because operations will run the system.

Where the start-up checklist sits

  1. 01
    Mechanical completion

    The system is built and inspected; category A punch is closed for MC.

  2. 02
    Ready for commissioning (RFC)

    Pre-commissioning is done and the subsystems may be energised or filled.

  3. 03
    Commissioning

    Function tests, cause and effect tests and run-in with the real medium.

  4. 04
    Pre-startup safety review (PSSR)

    A team review that the system was built and commissioned as designed and is safe to start.

  5. 05
    Ready for start-up (RFSU)

    The certificate that the system is safe to introduce hydrocarbons or its process medium.

  6. 06
    Start-up readiness (Go / No-Go)

    The last check on the day: everything the RFSU relies on is still true, and the people and supplies are in place.

The RFSU is a certificate signed once. The start-up checklist is run close to the start, because things change between the two: a permit reopened, a relief valve removed for repair, a punch item raised on a late walkdown.

The Go / No-Go requirements

GroupRequirementTypical evidence
Procedures and peopleStart-up and operating procedures issued; operators trained; emergency response updated and drilledProcedure numbers, training records, drill record
CompletionsCategory A punch open = 0; RFC certificates signed; PSSR done and pre-start-up actions closedPunch list, certificates, PSSR report
Safety systemsESD tested; fire and gas detection tested; cause and effect tested end to end; relief valves set and certifiedTest records, PSV certificates
IsolationsPermits closed, LOTO removed or handed to operations; temporary blinds and test equipment removedIsolation and spade registers
Utilities and suppliesPower, instrument air, nitrogen and cooling water available; spares, lubricants and chemicals in place; communications workingUtility status, first fill record, telecom ITRs

In the United States, OSHA 29 CFR 1910.119(i) requires a pre-startup safety review for new and significantly modified facilities covered by process safety management. Many operators apply the same discipline everywhere.

What is in the template

Start-up readiness checklist with system fields, a count line, an overall decision banner reading incomplete, and 15 requirements in five groups with Go or No-Go, evidence, by and date, followed by a decision statement and four signatures
The free start-up readiness checklist. The overall decision reads GO, NO-GO or INCOMPLETE as you fill it in.
SheetFields
Start-up readinessProject, document number, revision, system, description, planned start-up date, start-up lead, RFSU certificate number, PSSR reference. Count line and overall decision (formula). 15 requirements with Go / No-Go / N/A (drop-down), evidence, by and date; the punch line computes Go or No-Go from the open count. Decision statement and sign-off by commissioning, operations, client and TPI.
Readiness by systemOne line per system: punch A open, RFC signed, PSSR done, ESD and F&G tested, C&E tested, procedures issued, operators trained, LOTO cleared, utilities available, decision (formula: Go, No-Go or Incomplete), planned start-up and remarks. Counts at the top.

How it connects to the other records

The checklist is only as good as the records behind it. The PSSR checklist covers the safety review itself, the completion certificates include the RFSU certificate, and the cause and effect matrix and lockout tagout procedure cover two of the checks in detail.

Deskely Core holds the tag register, ITRs, punch and handover in one system of record, so the punch and certificate lines can be read from the records instead of counted by hand.

The Deskely products for this

Frequently asked questions

What is a start-up checklist?

The final Go / No-Go check before a commissioned system is started with its process medium, confirming procedures, training, punch, PSSR, safety systems, isolations and utilities are all in place.

What is the difference between RFSU and a start-up checklist?

RFSU is the certificate that a system is ready for start-up. The start-up checklist is run close to the actual start, to confirm nothing has changed since the certificate was signed.

Can a system start with open punch items?

Not with category A items open. Category B items may remain if they are listed, agreed and do not affect safe operation.

What is a PSSR?

A pre-startup safety review: a team check that a new or modified system was built and commissioned as designed and is safe to start. OSHA 1910.119(i) requires one for covered processes in the US.

Who makes the Go / No-Go decision?

The start-up lead with operations, commissioning and the client, each signing the checklist.

Is the system really ready, or is the count a week old?Deskely Core holds every ITR, punch item, test pack and certificate against its tag, and shows what still blocks each subsystem from its next milestone, start-up included.
  • In production since 2014
  • Thousands of daily users
  • On MODEC FPSO projects since 2016

Autonomous engineering runs on Deskely.

Talk to sales